General

Infrastructure with on-site water storage

Text Liliane VerwooldePhotography Buro Baars Infra & Advies

‘We bring it all together beautifully.’
‘We bring it all together beautifully.’

To complete Caravan Centrum Meerkerk on time, all parties had to work at pace. This was especially true of Buro Baars Infra & Advies and Baars Aannemerij BV, which were responsible for the infrastructure. The other parties could not get started until they had completed the groundworks associated with the building and installed the sewerage system.

“The work was prepared by a construction team,” says André Baars, owner and consultant at Buro Baars Infra & Advies. “Everyone contributed ideas on the most efficient approach, and the atmosphere was both positive and constructive. Thanks to this collaborative approach, we were able to complete the entire site layout within six
weeks.”

80% of the site is paved with a water-permeable surface.

On-site rainwater infiltration

Given the tight timescale, Buro Baars worked at pace from the outset. Preparations were already well under way before the permits had been issued. “An important requirement was that rainwater had to be stored and infiltrated on the site,” Baars says, describing this phase. “This was a fairly new development for us, so we had to look into it in some detail. We designed water-permeable paving using special types of stone, as well as a water-permeable surface for the caravan parking area. In total, 80% of the site is paved with this water-permeable surface, which has a coarse-grained foundation with the
required load-bearing capacity.” 

Flexible collaboration

The infrastructure was delivered by Baars Aannemerij BV, which followed the logistics schedule closely. “We plan everything as precisely as possible,” says site manager Rik Baars. “At the same time, we remain flexible. We did not need exclusive use of the 4,500 m2 site at all times. Areas where we were not working could
be used by others.”

Thanks to the collaborative approach, the entire site layout was completed within six weeks.

A cohesive whole

Once the building was complete, Baars Aannemerij returned for phase two: paving the area around the building. “That is typical of our work. We are the first on site and the last to leave. That is also what makes this project special. We bring it all together into a cohesive whole.” 

Question about this story? Ask your question

Who worked on Caravan Centrum Meerkerk

  1. infrastructureBuro Baars Infra & AdviesIn this story
  2. construction of the infrastructureBaars Aannemerij BVIn this story
  3. claddingCladding PartnersMentioned in A steel structure delivered at the fastest possible pace
  4. steel structureHJ MetaalbewerkingMentioned in A steel structure delivered at the fastest possible pace
  5. contractorAannemersbedrijf P. van LeeuwenMentioned in New caravan centre in Vianen
  6. clientCaravan Centrum MeerkerkMentioned in New caravan centre in Vianen
  7. architectVOCUS architectenMentioned in New caravan centre in Vianen
  8. engineering consultancyIBTMentioned in New caravan centre in Vianen
  9. façade contractorJM van Delft & znMentioned in New caravan centre in Vianen
  10. installation workBrandsenMentioned in New caravan centre in Vianen
  11. façade contractorJ.M. van Delft & zn.Mentioned in Curtain wall with panes measuring no less than 5.5 metres

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectCaravan Centrum Meerkerk
  • SubjectGeneral
  • CompanyBuro Baars Infra & Advies
  • CompanyBaars Aannemerij BV
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.