New caravan centre in Vianen
Text Aannemersbedrijf P. van LeeuwenPhotography Aannemersbedrijf P. van Leeuwen

The new commercial building was completed seven months after the first pile was driven. Aannemersbedrijf P. van Leeuwen worked closely with Caravan Centrum Meerkerk and the partners in the construction team from the outset. This laid the foundations for quality and swift delivery.
Construction team drives strong performance

“We strongly favour a construction team approach based on equal, transparent collaboration, because everyone brings their expertise to the table from the design stage onwards,” stresses Cees den Otter, director of the contracting firm. “This delivers the best quality, price and programme. Most of our turnover comes from construction team projects and developments that we undertake ourselves or jointly with others. We are therefore used to taking responsibility. On this project, ahead of the final commission, we started working out the steel structure to secure the steel supply and get ahead of further price rises. It all comes down to trust.”
Expertise
The construction team comprised the client, VOCUS architecten, engineering firm IBT, project manager/site supervisor Aad van den Beukel and trusted co-makers. “We have been active in commercial and residential construction for over forty years, and we have worked with some suppliers for almost as long, which enables us to make optimisations,” says Den Otter. “We did this with HJ Metaalbewerking on the steel structure. Together with façade contractor JM van Delft & zn, we worked with the architect on the building’s glazed entrance.”

“We put forward proposals with Cladding Partners for cost-effective façade cladding with high insulation values and a trapezoidal profile in line with the design. Our regular partner Brandsen once again delivered excellent installation work. The energy-neutral building features a heat pump and PV panels, as well as high-quality insulation and excellent airtightness. We used responsibly sourced FSC-certified timber for the woodwork. It is a highly sustainable project.”
Delivering
“We installed the first foundation piles three months after signing the contract, despite uncertainty over the supply of building materials. Our skilled teams pulled out all the stops, sometimes working outside normal hours, to pour the concrete floor before the summer. This milestone was crucial to completing the fit-out in the autumn and achieving the planned handover in early December. We gave the client the flexibility to fit out the workshop during construction, which was greatly appreciated.”
Caravan Centrum Meerkerk moved into its new premises in Vianen in mid-December. The ground floor houses offices, a camping shop, a warehouse and a modern workshop, while the spacious first-floor showroom displays new and used caravans and awnings. Caravan owners can bring their vehicles to the workshop for servicing and repairs.
Design vision
“It is all about the way the business operates: an attractive space to showcase caravans and engage visitors, combined with a workshop,” says Michael Noordam, architect and owner of VOCUS architecten. “Our practice is known for talking to clients to understand their requirements and inspire them, making it possible to achieve what once seemed unfeasible. At the heart of our design is the inviting glazed entrance, which naturally draws visitors in and offers them a warm welcome. The two parts of the building are connected to it, while remaining distinct, with a difference in height and façade detailing that makes the building appear lower. This allows us to meet the urban planning requirements while giving the larger whole a welcoming appearance.”
Pride
“Once again, we have had the opportunity to deliver a fine, sustainable project for a long-standing client,” Den Otter concludes. “Thanks to everyone’s efforts, everything went smoothly, and we thoroughly enjoyed working on it. We are proud to add Caravan Centrum Meerkerk in Vianen to our portfolio and welcome enquiries about similar projects!”
A business enquiry for Cladding Partners? Get in touch
Who worked on Caravan Centrum Meerkerk
- construction of the infrastructureBaars Aannemerij BVMentioned in Infrastructure with on-site water storage
- steel structureHJ MetaalbewerkingMentioned in A steel structure delivered at the fastest possible pace
- contractorAannemersbedrijf P. van LeeuwenIn this story
- clientCaravan Centrum MeerkerkIn this story
- architectVOCUS architectenIn this story
- engineering consultancyIBTIn this story
- façade contractorJM van Delft & znIn this story
- installation workBrandsenIn this story
- façade contractorJ.M. van Delft & zn.Mentioned in Curtain wall with panes measuring no less than 5.5 metres
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCaravan Centrum Meerkerk
- SubjectConstruction projects
- CompanyAannemersbedrijf P. van Leeuwen
- CompanyCaravan Centrum Meerkerk
- CompanyVOCUS architecten
- CompanyIBT
- CompanyJM van Delft & zn