General

Koningsplein, Amsterdam | More than 160 tonnes of temporary steel for basement construction

Koningsplein, Amsterdam | More than 160 tonnes of temporary steel for basement construction

Building a new basement beneath ten listed buildings in the heart of Amsterdam. This called for, among other things, an ingenious support structure using countless tonnes of temporary steel. Welding and installation company Van Pommeren took on the challenge during the second phase of the Koningsplein project. Van Pommeren also supplied all the permanent steelwork.

“This kind of work suits us well,” says Gerrit van Leeuwen, project manager at Van Pommeren. “In the seventeen years since we were founded, we have grown into a full-service construction company, with specialists in the engineering, fabrication and installation of unique structures. Clients working on complex, unusual projects are increasingly turning to us. Fine examples include Post Utrecht on the Neude and Amsterdome, EMA and Olympic Plaza in Amsterdam. Koningsplein certainly belongs on that list too.”

The support structure consists of a series of ‘tram tracks’ made from steel beams and girders.

Collaborative structural design

Van Pommeren had already been involved in the first phase of Koningsplein. As in the second phase, listed commercial buildings were renovated and partly converted into flats. “In terms of construction, phase 2 is completely different,” says Van Leeuwen. “Here, we are creating an entirely new basement, which will be used by a supermarket. High-end shops and flats will be built above it.” Van Pommeren and several other contractors were brought into the project at an early stage. Among other things, they worked with Pieters Bouwtechniek and Burgland Bouw to develop the construction method. Van Leeuwen says: “That laid the foundations for the close and positive collaboration that is now paying dividends on site.”

One of the steel towers supporting the ‘tram tracks’.

Steel support structure

Van Pommeren supplied and installed, among other things, the temporary steel structure needed to build the basement. “The existing bicycle basement has been excavated to a greater depth,” explains Van Leeuwen. “This meant that the existing basement and ground-floor slabs had to be removed. That left a large opening between the basement and first floor. Our support structure bridges this gap. It consists of a series of ‘tram tracks’ made from steel beams and girders, which lift the building at first-floor level. The tracks are supported by steel towers resting on the newly installed piled foundations. At the same time, we installed part of the permanent steelwork, which could not be fitted later because of the limited space.” Van Pommeren also used temporary steel to support several listed walls during the basement works. Temporary steel was also used in the restoration of a small listed outbuilding, which was completely dismantled. Van Pommeren used a total of 160 tonnes of temporary steel.

Basement nearing completion

Work on the basement began in February 2019. First, the new piled foundations were installed. Van Pommeren then assembled the support structure. It was then pressurised, allowing the building to be safely lifted so that the ground-floor and basement slabs could be demolished. “It was quite literally a tense operation,” says Van Leeuwen. “No deformation of the building was allowed during the basement works.” The demolition is now complete and the basement has been excavated. The new basement walls and floor have been cast, and the ground-floor slab will also be in place before the summer building shutdown. Once it has cured, Van Pommeren will install the remaining permanent steelwork on top. The temporary steel will then all be removed. “The permanent steelwork is a heavy structure made up of HEB and HEM beams and columns,” explains Van Leeuwen. “It takes over the function of the old brick walls and allows for large spans.”

The steel towers rest on the newly installed piled foundations.

Upper floors

For the upper floors, Van Pommeren is supplying and installing all the permanent steelwork, both load-bearing and non-load-bearing. Van Leeuwen says: “This mainly includes steel stairs, steel decking, balconies and the old steel sections and wrought ironwork in the front façade of one building, as well as the steelwork for the lift and plant rooms. The main challenge with the upper floors is setting out. We are dealing with different floor levels, and everything ultimately has to be level. And because this is a renovation, unexpected issues can arise. You have to allow for them, but also resolve them on site. The project is also a logistical challenge. We are working in a postage-stamp-sized space in the heart of Amsterdam. Getting all the steel to site and lifting it into place is a complex puzzle.”

Temporary steel

Outstanding work on site

Van Leeuwen stresses that good collaboration with the contractor, structural engineer and other contractors is crucial. “A project of this scale and complexity can only succeed if everyone genuinely works together to deliver it. That is exactly what is happening here. Communication is direct, we respond quickly and we constantly work things through together.” Van Leeuwen adds: “We can draw up the most impressive plans, but it is our people on site who make them happen. They are doing an outstanding job on this project. Thanks to their hard work and craftsmanship, Koningsplein will soon be a first-class place to live and shop.”  

Question about this story? Ask your question

Wie aan Koningsplein werkte

  1. ContractorPieters BouwtechniekIn this story
  2. ContractorBurgland BouwIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKoningsplein
  • SubjectGeneral
  • CompanyPieters Bouwtechniek
  • CompanyBurgland Bouw
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.