Earthworks and infrastructure partner lays solid foundations for new-build RottaNova
Text Lieke BousemaImage VMV Projecten B.V.

Excavating a deep basement under remediation conditions, including dewatering, installing site facilities or carrying out demolition and earthworks in an urban setting: it is all in a day’s work for VMV Projecten B.V. The company, based in Renswoude, established a firm footing in the construction industry more than twenty years ago. Since then, it has completed more than a thousand earthworks and infrastructure projects, including its current work on the RottaNova apartment building in Rotterdam.
VMV Projecten B.V. is a trusted earthworks and infrastructure partner for clients in the construction and property sectors. Its professional team provides every service imaginable, from engineering to soil remediation, earthworks, external drainage, drainage systems, surfacing, landscaping and site works.

From excavation pit to sheet piling
With more than a thousand infrastructure and earthworks projects completed, VMV Projecten B.V.’s work underpins countless buildings and property developments, says director Henk Hazeleger. “Particularly in the west and centre of the Netherlands, homes, shops, industrial units and entire neighbourhoods have been built on land that VMV Projecten B.V. has remediated, surfaced, prepared for construction, paved, planted and/or fitted with retaining structures. Then there is the work that eventually becomes invisible. Think, for example, of excavating construction pits, installing sewers and pressing or vibrating sheet piles into the ground. In recent years, we have specialised in excavating and preparing large, complex construction pits for building work. Thanks to our extensive fleet of machinery, we can carry out virtually any type of earthworks project.”
RottaNova in Rotterdam
A fine example is RottaNova, a new apartment complex with 258 homes for sale and rent, spread across two residential towers measuring 67 and 61 metres. The ground floor will house shops, restaurants and cafés, creative workspaces and a public bicycle parking facility, with a 2-storey underground car park for 100 vehicles below. RottaNova is being built on the green strip between Hoogstraat and Markthal in central Rotterdam. The design is by Frits van Dongen architecten, commissioned by developer Van Herk Groep. NEOO is responsible for development management, while the construction consortium of J.P. van Eesteren and Dura Vermeer Bouw Zuid West is responsible for delivery, commissioned by RottaNova Ontwikkeling B.V.
Excavated twice
VMV Projecten B.V. was responsible for setting up the RottaNova construction site. “On behalf of the construction consortium, we removed the original paving and laid concrete panels suitable for heavy traffic across the site,” says VMV Projecten B.V. project manager Gerrit van Kruistum. “We then began excavating for the two-storey car park.” One unusual aspect of the project is that the basement has to be excavated twice, Hazeleger explains. “Rotterdam originated around 750 years ago, right here. The site is therefore of great archaeological value. That is why BOOR, the archaeological service of the Municipality of Rotterdam, carried out an archaeological investigation. And it proved worthwhile, as valuable finds were made during excavation.” Hazeleger and Van Kruistum cite the remarkably intact remains of a sluice channel built in the Middle Ages to combat flooding. Other finds included old weapons, tools, jewellery and kitchen utensils. “In total, we excavated around 40,000 tonnes (25,000 m3) of clay and peat, after which most of the pit was filled with clean sand for the piling rig. Once the piling work is complete, we will excavate the construction pit again and prepare it for the foundation structures. We will also backfill around the car park. Where necessary, the construction site facilities will be expanded.”
According to Van Kruistum, the biggest challenge is the busy urban construction site. “As there is a market on Tuesdays and Saturdays, we cannot schedule deliveries on those days,” he says. “The construction pit is also quite deep, so we have to work between the waling frames during excavation. Part of the pit was excavated under remediation conditions. Combined with the archaeological investigation and a degree of wellpoint dewatering, this is where our expertise really comes into its own.”
Question about this story? Ask your question
Wie aan RottaNova werkte
- earthworks and infrastructure partnerVMV Projecten B.V.In this story
- architectFrits van Dongen architectenIn this story
- developerVan Herk GroepIn this story
- development managementNEOOIn this story
- construction consortiumJ.P. van EesterenIn this story
- construction consortiumDura Vermeer Bouw Zuid WestIn this story
- clientRottaNova Ontwikkeling B.V.In this story
- archaeological investigationBOORIn this story
- development consortiumdevelopment consortium NEOOMentioned in Building for the future on a historic site on the Rotte
- lead structural engineer and coordinating structural engineerMovares | Zonneveld IngenieursMentioned in Building for the future on a historic site on the Rotte
- uitvoeringscoördinatie van de (hoofd)draagconstructieMovaresMentioned in Building for the future on a historic site on the Rotte
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRottaNova
- SubjectYearbook
- CompanyVMV Projecten B.V.
- CompanyFrits van Dongen architecten
- CompanyVan Herk Groep
- CompanyNEOO
- CompanyJ.P. van Eesteren


















