The circular façade as a buildable compromise
Text Tjerk van DuinenImage Leebo Intelligente Bouwsystemen

On Zeeburgereiland in Amsterdam, three former industrial silos are being converted into a public urban complex. Cinema, sport, hospitality, workspaces and a public rooftop park are housed in a robust concrete structure with a distinctive industrial past. The silos’ cantilevered upper sections are being given a special envelope: not a thin skin, but an intelligent system that makes an architectural vision possible at an affordable cost.
Leebo Intelligente Bouwsystemen is responsible for the project’s façades. Site manager Johan van Nimwegen stresses that, while the façade may look understated, it is far from technically straightforward. What appears from the quayside to be one continuous circle is in fact a carefully assembled system of prefabricated elements, each with its own role in the structure, installation and finish.

Segments
The silos’ upper sections sit on slender neck structures and are clad in aluminium composite cassettes (LeeBond) with narrow strips of glazing. Each upper section forms a complete circle made up of 24 segments. Van Nimwegen explains that this segmentation was essential to making the façade buildable. “The elements are manufactured entirely in the factory: the steel frame, insulation, vapour-open and vapour-tight membranes, and window frames are all integrated. Even the glazing is already in place when they arrive on site. The curvature is not created on site, but built into the element itself. The panels are segmented, milled to shape and then rolled, resulting in a curved façade at the cost of a straight one.”
Installation
According to Van Nimwegen, this prefabricated approach has a direct impact on installation. Wall sections about four metres wide are suspended using a hook system, aligned and fixed in place. One three-storey silo can be made wind- and watertight in about five days. This pace is necessary because the site is complex and several trades need to follow one another in quick succession.

Backing structure
One important difference is between the neck and the upper section. Black sandwich panels have been used in the neck, but will ultimately remain out of sight. Van Nimwegen points out that a backing structure with façade panels will be added to the outside, while plasterboard walls will be installed on the inside. Here too, everything is segmented, because the window frames are as well. “The upper section gets its distinctive appearance from the champagne-coloured cassettes. They are deep and provide solar shading. They keep out the high summer sun while allowing low winter light to enter. A matt coating prevents reflections towards the surrounding area.”
Façade design
The installation sequence is tightly controlled. First, the elements are fitted and closed, followed by sealing and insulation. Only then can another contractor install the glazed strips between the floor edges. These have no structural function, Van Nimwegen stresses, but they are key to the façade’s appearance. Only once they are in place can Leebo fit the final external finish. This marks the moment when the building gets its “final jacket”.
According to Van Nimwegen, the project shows that the façade here is not decoration, but an instrument. “A system that brings together aesthetics, technology and collaboration, and in which the industrial heritage is not concealed but carefully given a new finish.”
Question about this story? Ask your question
Wie aan De Silo's werkte
- facadesLeebo Intelligente BouwsystemenIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDe Silo's
- SubjectFaçades, roofs & roof gardens
- CompanyLeebo Intelligente Bouwsystemen