2,778 precast concrete elements for High Five
Text Lieke BousemaImage Stabiel Management

A complete floor in four days thanks to smart prefabrication
On Utrecht Science Park, construction is moving ahead at pace on High Five, a mixed-use development comprising 721 student studios and 200 student rooms across two residential towers rising more than 70 metres, above a 6-metre-high podium with hospitality, sports and residents’ facilities. Developer and contractor VORM 2050 aims to build this project 20% more cheaply and 50% faster. Stabiel Management’s smart, cost-effective prefabricated construction system is making a significant contribution.
Stabiel Management is a long-standing design and delivery partner of VORM 2050 and was involved in High Five from the tender phase. “Initially, the structure of High Five was going to be entirely cast in situ,” says Henri van Nistelrooy, technical adviser/project manager at Stabiel Management. “However, given the benefits of prefabricated construction, we were asked to investigate alternative options. This resulted in a largely prefabricated frame, allowing VORM 2050 and building owner Stichting Studentenhuisvesting (SSH) to benefit from a shorter construction period, higher build quality, lower costs, less transport, lower nitrogen emissions and a safer working environment.”
Finding the right tipping point
Below the second-floor slab, the project is cast in situ, Van Nistelrooy explains. “This was a deliberate choice because of the distinctive design of the lower section, where the columns are not directly beneath the walls. From the 2nd to the 21st floor, however, the frame is built entirely from precast concrete elements and steel beams. This enables us to complete a floor in four days. During the preparatory phase, we worked with lead structural engineer Pieters Bouwtechniek to find the right point at which to switch between construction methods. We also divided the structure into manageable elements that can be produced, transported, lifted and installed safely, both technically and economically.”
Smart and efficient
As well as the design and engineering, Stabiel Management is responsible for producing and installing the prefabricated frame, which consists of 1,088 precast concrete walls, 1,452 solid floor slabs, 132 concrete staircases and 106 steel beams, Van Nistelrooy says. “Following the structural design, VORM 2050 has also extended the prefabrication concept to the fit-out. High Five will also use prefabricated façade elements, bathrooms and installation skids. During the four days we spend completing a floor, we also take the bathrooms and fit-out materials up to that level. This means these products no longer need to be transported using the internal lifts. We believe that is another smart and efficient way to build.”
Een zakelijke vraag aan Stabiel Management? Get in touch
Wie aan High Five werkte
- kozijnen en vliesgevelsFacédoMentioned in Build more cheaply and quickly with prefabricated façade elements
- prefabricated timber frame elements
VIANENMentioned in Build more cheaply and quickly with prefabricated façade elements - clientStichting Studenten Huisvesting (SSH)Mentioned in Build more cheaply and quickly with prefabricated façade elements
- construction partnerSorba ProjectsMentioned in Build more cheaply and quickly with prefabricated façade elements
- ontwikkelaar en aannemerVORM 2050In this story
- building ownerStichting Studentenhuisvesting (SSH)In this story
- Lead structural engineerPieters BouwtechniekIn this story
- architectural practiceOZMentioned in Build faster and more cost-effectively with prefabricated façade elements
- installation companyKuijpers Uitvoering & Advies BVMentioned in Build faster and more cost-effectively with prefabricated façade elements
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectHigh Five
- SubjectModular construction
- CompanyStabiel Management
- CompanyVORM 2050
- CompanyStichting Studentenhuisvesting (SSH)
- CompanyPieters Bouwtechniek