‘Wood wherever possible’
Text Lieke BousemaImage Vivid Vision

A modern, sustainable and future-proof office building in a former agricultural area, meeting the circularity criteria set by the municipality of Hendrik-Ido-Ambacht. With this ambition from Persy Control Services (PCS) in mind, WSP developed a structural design with an almost entirely timber frame and a strong focus on design for disassembly, fire safety, building physics and BENG.
WSP is a global consultancy and engineering firm operating in the fields of buildings, infrastructure, the environment, water and energy. In the Netherlands, its team comprises 480 dedicated experts who work passionately every day to create a future-proof living environment where people can live, work and spend time safely and healthily. The new build for PCS is an excellent calling card. WSP was brought on board at an early stage by building contractor Van Baaren and timber construction company Derix to contribute to the structural design of the new office building. “We already knew Van Baaren and Derix from an earlier project in Uithoorn,” says Project Leader, Building Structures, Bas de Leijer. “That meant we could also apply our structural expertise to this project.”

Circular and demountable
Ambachtsezoom business park is located in a former agricultural area, he explains. “The municipality of Hendrik-Ido-Ambacht has set strict circularity requirements for the development of this business park. For example, all new buildings on the site must be designed for disassembly. The use of adhesives, expanding foam, PVC and sealant is not permitted on site. Welding and pouring concrete are also prohibited. No composite products could be used, and the building had to be energy-neutral. Based on these principles and using the architectural design by EVA architecten as our starting point, we began sketching out the primary structure. We soon brought in our expertise in areas such as fire safety, building physics, BENG and nitrogen emissions.”
Timber construction
The new PCS office building has a floor area of 1,600 m2 and is designed as a two-storey volume raised above ground level, allowing parking beneath the building and out of sight. “There is a climate barrier between the underground car park and the office floors above,” says De Leijer. “We compared several options, paying particular attention to thermal bridging, fire safety and structural performance. We then developed the building in outline as part of the construction team and refined the design further.” One of the decisions was to use a timber structure. From the ground floor upwards, the new building is constructed with glulam columns and beams combined with CLT floors. De Leijer says: “Timber proved to be the best choice for making the building Paris Proof. Wood is a natural product, lightweight and aesthetically pleasing, and it creates a healthy working environment. It also has the lowest carbon footprint of all conventional building materials. In a supply chain analysis, we compared our design with a steel version, taking into account production, transport and installation. The results show that our timber structure produces 25% less CO2 equivalent emissions per square metre! This is not only because timber production causes fewer emissions, but also because wood is relatively lightweight for the load-bearing capacity of the material. This means the foundations can be lighter, saving around 20 per cent on the concrete used in the foundations and piles.” The building’s stability is provided by a prefabricated concrete core with concrete walls, connected using specially designed demountable connections.
Energy-efficient and comfortable
The new PCS office has a transparent façade with extensive glazing, which brings specific requirements. “For example, in relation to the BENG requirements and the need to maintain a comfortable indoor climate,” says De Leijer. To develop an effective solution, they also brought in colleague Moniek van Leth, Senior Adviser in building physics, acoustics and fire safety. “Together, we determined the right insulation values for the glazing,” she says. “We also optimised the projecting façade bands to provide precisely the right amount of solar shading. This significantly reduces the building’s cooling load. The upper surfaces of the façade bands feature a specially selected mix of herbs that attracts bees, butterflies and other insects. The building therefore also contributes to biodiversity and nature-inclusive development in the area. Solar panels on the roof meet both the building’s own energy needs and the energy consumption of all its users, enabling the building to operate as an energy-neutral facility.”
60-minute fire resistance
To ensure fire safety in the new building, WSP agreed the requirements for the underground car park and office floors with the safety region. “This led, for example, to a requirement for 60 minutes’ fire resistance against structural collapse,” says Van Leth. “The structure was dimensioned accordingly, leaving sufficient timber after 60 minutes of fire exposure to keep the building standing. This gives people in the building time to escape safely and gives the fire service sufficient time to extinguish the fire.” As the office building is located 8.5 kilometres from the De Biesbosch Natura 2000 site, nitrogen emissions during both the construction and operational phases were also analysed. Several nitrogen calculations were carried out, showing that the project
will not cause an increase in nitrogen deposition in De Biesbosch.
A business enquiry for WSP? Get in touch
Wie aan Kantoorgebouw PCS Hendrik-Ido-Ambacht werkte
- mechanical and electrical installationsElektroservice HollandMentioned in Sustainably and circularly developed office building
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectPCS Hendrik-Ido-Ambacht office building
- SubjectModular construction
- CompanyWSP