Residential and non-residential construction
Berenkuil, Eindhoven | 300 student homes in five months

Eindhoven has been struggling with a huge housing shortage for years. This is a particular deterrent to international students considering studying in Eindhoven. With 300 temporary student homes at Berenkuil, Eindhoven took a step in the right direction. Four residential blocks were built here in just five months.
Maximising prefabrication and careful planning
Max Smits, project manager at Jan Snel, seems little impressed as he explains that the order came in on 24 June 2019 and the first homes were completed as early as October that year. Just two months later, all 300 homes were ready to rent. “That’s where our strength lies.” Although, for this rapid pace to be achieved, everything really had to go right….

Residents have their own bathroom facilities.
Four residential blocks
The 300 ready-to-use homes measured 6 x 3 m and were divided among four residential blocks, each with four floors. Each home had its own kitchen and bathroom facilities. The client opted not to install a lift, keeping the homes affordable. Communal facilities were provided, including a laundry and meeting room, 16 parking spaces and bicycle parking for around 400 bikes.
A fast-track planning process
Given the short construction period, Jan Snel got moving straight away, even though this meant taking risks. “A planning application process takes eight weeks on average,” says Smits. “In most cases, it is then extended by another six weeks. But everything for Berenkuil was approved within a week and a half. That short period was packed with an incredible number of meetings and countless phone calls, but everything ran like clockwork.”

The homes are compact and fully equipped.
Preparation and prefabrication
Since Jan Snel could not have anticipated that the permits would come through so quickly, it began work in advance at its own risk. Smits: “We had already started producing the units, including prefabricating the concrete foundation pads, timber walls and roofs. The steel structure was already being engineered, and preparations for the bathrooms and kitchen units were well under way. The aim was to prefabricate the units as much as possible, so that only the services needed connecting on site. The walls and ceilings also still needed painting.”
Hard graft
To create a cohesive whole, metal cladding was chosen for the ground-floor units, with timber cladding for the three storeys above. “It was hard graft,” Smits admits. “We worked six days a week, with 12-hour shifts. At the busiest times, there were 100 people on site. It was up to us to let each team know when they needed to carry out their tasks. The pace was demanding for our client too. Normally, there is still plenty of scope to make or reverse decisions during construction. That was almost impossible this time.”
The homes at Berenkuil have been built for a period of 15 years. After that, Woonbedrijf will find a new location for the units. Smits is pleased with the result: “As a student, I would have loved to live here. The units are small but fully equipped. Eindhoven has made great progress.”
Question about this story? Ask your question
Wie aan Studentencomplex Berenkuil werkte
- modular builderJan SnelMentioned in Jan Snel builds 300 future-proof student homes in record time in Eindhoven
- clientWoonbedrijfIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBerenkuil student accommodation
- SubjectResidential and non-residential construction
- CompanyWoonbedrijf


















