109 heat pumps on the roof and a smart drainage system
Nijhof Installatie handles all electrical and mechanical installations.

109 rooftop heat pumps and a smart drainage system

Building Services Engineering for 107 Apartments in Lelystad

At Hanzepark in Lelystad, Ter Steege is building Spoordok: three connected residential towers with 107 rental apartments and common areas for the Centrada housing association. Nijhof Installatie is handling all electrical and mechanical installations. Project Manager Roy Alferink discusses the rooftop heat pumps, a new type of drainage system, and the value of getting involved early in the planning process.

Nijhof is a full-service contractor and part of the Nijhof Group, along with Willemsen Installatie and Eefting Installatie. The company focuses on both large-scale and custom residential construction projects and completes approximately 150 homes annually. Alferink: “The contractor knew us from a previous project. Apparently, we made a good impression.”

Room-by-room heating

Each apartment will be equipped with its own Panasonic air-to-water heat pump, with the outdoor units located on the roof. Heating is provided via underfloor heating and can be controlled separately for each living area. Ventilation is centrally controlled for each tower, with a ventilation system on the roof. Each apartment has its own adjustable damper module. Alferink: “This was a deliberate choice. It’s low-maintenance: no maintenance is required inside the apartment. You replace the filters on the roof. That saves us from having to schedule appointments with residents.”

Space Savings with SuperTube

For the wastewater drainage, Nijhof chose Geberit’s SuperTube system. According to Alferink, that choice makes this project particularly special. “The system requires virtually no connection-free zones, so you don’t have to connect the bottom floor separately. That makes installation a lot easier. Plus, it also serves as a sound-insulating pipe.”

109 heat pumps on the roof

The biggest challenge lies in the planning. Alferink: “It’s going to be quite a task to install 109 heat pumps on the roof and have the project ready for handover by the end of December. But we’re happy to take on that challenge.” What makes the project special for him? The excellent collaboration with all construction partners and their early involvement. “We contributed ideas during the design phase, which is why, for example, we’re using a different type of heat pump than originally planned.”.
”It's always nice when you can tailor the design to your liking."  

Gerelateerde artikelen

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

Send us a message

Wij gebruiken cookies. Daarmee analyseren we het gebruik van de website en verbeteren we het gebruiksgemak.

Details

Kunnen we je helpen met zoeken?

Bekijk alle resultaten