Façades, roofs & roof gardens

A façade contractor adding value

Text Roel van GilsImage WVH Gevelprojecten

The Blox illustreert waar WVH Gevelprojecten goed in is: complexe, esthetische hoogbouwprojecten in krappe binnenstedelijke condities, waarbij prefab, coördinatie en logistiek samenkomen.
The Blox illustreert waar WVH Gevelprojecten goed in is: complexe, esthetische hoogbouwprojecten in krappe binnenstedelijke condities, waarbij prefab, coördinatie en logistiek samenkomen.

The aesthetic, building-physics and structural envelope of The Blox is fully prefabricated under controlled conditions at WVH Gevelprojecten. The ready-to-install timber frame elements are then installed on site without using a tower crane or scaffolding.

“Facédo asked us at an early stage to help consider how to seal the façade of The Blox,” says Helen Nossin, Head of Sales and Projects at WVH Gevelprojecten. “Together with VORM Bouw, we looked at whether building the entire tower using timber frame elements would be feasible, both technically and financially. And we had just a few months to do it. It proved to be a winning formula: VORM Bouw ultimately awarded us the project, and we could prepare for the build.”

Assembly line

The scope for WVH Gevelprojecten was clear, according to Nossin: “The contractor is building the concrete frame, while we are supplying the building-physics and structural envelope as ready-to-install timber frame elements. All the elements are fully prefabricated at our facility and fitted with façade cladding (aluminium composite panels, aluminium box sections and profiled aluminium sheets), lighting and aluminium frames. Facédo installs the frames on our assembly line, after which each element is carefully packaged and delivered to the site as a single unit.”

OLYMPUS DIGITAL CAMERA

Protective coating

One distinctive feature is the protective coating WVH Gevelprojecten applies to every element. “It is our own development and is unique in the Netherlands,” says Rick van Veghel, Project Manager at WVH Gevelprojecten. “The coating is sprayed around the timber frame element and into all the frame openings. This gives the elements better protection during construction against the weather, construction waste and damage, significantly improving the quality and durability of the envelope.”

780 elements

Production and logistics are crucial to this project. “We started production in June, and the first batches were installed on site in October. We are supplying 780 elements in total,” says Nossin. “Our factory is currently producing four elements a day for The Blox, which are then stored on site. They are subsequently taken to a temporary storage facility close to the construction site and delivered just in time.” Fire safety, wind and watertightness, and quality can all be demonstrated. “Tests carried out in advance, including SBI fire tests, confirmed that the external façade achieved fire class B. We are now even developing a timber frame façade element with fire class A2.”

Lifting system 2.0

To enable installation without a tower crane or scaffolding, WVH Gevelprojecten developed a lifting and winch system. “It is an advanced version of our existing lifting system, which was used on the Clubhouse Boompjes project in Rotterdam. It minimises the safety zone and avoids disruption to the surrounding area, as there is no need to close the main road because of the risk of falling objects,” says Van Veghel. “Using the certified lifting system 2.0, we install six timber frame elements stacked vertically in each bay, then move on to the next bay.”

1:1 mock-up

According to Nossin, The Blox demonstrates what WVH Gevelprojecten does best: complex, aesthetically ambitious high-rise projects in constrained urban settings, where prefabrication, coordination and logistics come together. Van Veghel says: “By getting involved early in the process, we can put our stamp on the detailing and demonstrate it visually to the architect and client with a 1:1 mock-up. There are many façade contractors in the Netherlands, but few work the way we do. The client is free to choose the frame supplier and type of façade finish. We then take care of the entire technical design and coordination, delivering a complete concept to ensure the build runs smoothly and efficiently.” 

“We are committed to taking the burden off our clients. Our whole WVH team contributes to this, from estimating through to delivery,” says Van Veghel in closing. The final elements for The Blox are expected to be installed before the 2026 Christmas break.    

Have a business enquiry for Facédo Geveltechniek BV? Get in touch

Who worked on The Blox

  1. constructionVORM BouwMentioned in Construction begins on The Blox in The Hague’s Binckhorst
  2. designLEVS ArchitectenMentioned in Construction begins on The Blox in The Hague’s Binckhorst
  3. designFLUX ArchitectureMentioned in Construction begins on The Blox in The Hague’s Binckhorst
  4. complete structural shellDESAMentioned in Another storey every eight days: building to a tight rhythm
  5. precast wallsMombarg BetonMentioned in Another storey every eight days: building to a tight rhythm
  6. facade elementsWVH GevelprojectenMentioned in Another storey every eight days: building to a tight rhythm
  7. CalculationsSnijders IngenieursgroepMentioned in Precast frame on an unprecedented scale
  8. Aluminium framesFacédoMentioned in Pre-construction planning is key to successful façade projects
  9. prefabricated energy unitsERA Prefab SystemsMentioned in The Blox as a blueprint for a new way of building
  10. sanitary installationsInstallatiebedrijf J.C. KersbergenMentioned in Craftsmanship 2.0
  11. Sovent teesGeberitMentioned in Craftsmanship 2.0

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectThe Blox
  • SubjectFaçades, roofs & roof gardens
  • CompanyFacédo Geveltechniek BV
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.