Another storey every eight days: building to a tight rhythm
Text Roel van GilsImage DESA

DESA is carrying out the complete structural shell for The Blox, the 130-metre residential tower in the Binckhorst district of The Hague, on behalf of VORM Bouw. The company is responsible for the entire shell, from engineering through to construction. The tower rises by one storey every eight days, following a tightly controlled rhythm.
The first four storeys were cast entirely in situ, including the walls. From the fourth floor upwards, DESA is installing precast walls supplied by Mombarg Beton, while all the floors are still being cast in situ using traditional methods. “Each storey is completed in an eight-day cycle,” says Ata Turkoglu, project manager at DESA. “With a close-knit team of around 25 people on site, we can maintain this tight rhythm. This is, of course, thanks to our continuous collaboration with the VORM Bouw team.”

Safety is the top priority
Working at height inevitably carries risks, which is why safety is a top priority at DESA. “Our people are protected on site and sheltered from the wind by a climbing scaffold with wind and safety screens. It’s the ‘object’ with the distinctive yellow sheeting around the building,” explains Turkoglu. “We also make extensive use of the tower crane, not only for logistics but also for safely hoisting large precast elements and installing the loggias afterwards. It is therefore very valuable to us that WVH Gevelprojecten does not depend on the tower crane to install the façade elements.”
Technical challenges at height
According to Turkoglu, one of DESA’s biggest challenges is creating openings in the building spanning as many as three storeys. “This calls for unique structural solutions, such as the use of large steel A-frames. Each weighing more than twenty tonnes, these A-frames serve both a structural and an architectural purpose. They create cut-out terraces (in other words, internal neighbourhoods) that give The Blox its distinctive appearance. These cut-outs recur at several levels, making the project technically challenging.”

DESA is responsible for the complete structural shell, including installing the formwork and support systems and moving the climbing scaffold. “Thanks to close collaboration between the teams, both on site and with our client and other subcontractors through the project management team, we can organise the construction workflows tightly and maintain a fast pace.” The schedule calls for completion in December 2026, but Turkoglu expects the work to be finished as early as November 2026.
Een zakelijke vraag aan Desa Construction? Get in touch
Who worked on The Blox
- precast wallsMombarg BetonIn this story
- facade elementsWVH GevelprojectenIn this story
- prefabricated energy units
ERA Prefab SystemsMentioned in The Blox as a blueprint for a new way of building
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectThe Blox
- SubjectModular construction
- CompanyDesa Construction
- CompanyMombarg Beton
- CompanyWVH Gevelprojecten