New ING headquarters shows what sustainable construction looks like today
Text and images Sanitair-Installatie Hoogendoorn B.V.

RAINWATER AS A SMART RESOURCE
Construction of the new ING headquarters, Linden, is visibly focused on the future. The structural work is nearing its highest point, while fit-out is already in full swing on the lower floors. A building that impresses not only with its scale, but above all with its sustainability ambitions. Sanitair-Installatie Hoogendoorn is playing its part in the success of this project.
“We joined the project more than two years ago, following a tender,” says Michiel Karels, project manager at Hoogendoorn. “During the pre-construction phase, we worked with the project team to develop the entire design in 3D/BIM. We carried out numerous clash checks, allowing us to resolve potential issues during the design phase. This makes the work on site more straightforward and faster, and opens the door to prefabrication.”

A well-designed system
At Linden, Hoogendoorn is responsible for all the sanitary installations. These range from water supply and drainage to fire hose reels, dry fire mains, rainwater drainage and domestic water systems. It is a complete package, commissioned by Klimaatservice Holland. Sustainability is given a very practical application in the project through a well-designed rainwater reuse system. “This is a project where everything comes together: technology, collaboration and smart planning. Retention crates have been installed on the roofs, combined with drainage outlets fitted with smart flow control valves. These valves are controlled by a weather computer, which retains water during dry spells and releases it in advance when rain is forecast.”
Excess rainwater is collected in a 250,000-litre tank next to the building. The water is filtered and then used to flush toilets and urinals. “During prolonged dry spells, we top up the retention crates on the roofs from the same tank,” says Karels. “That keeps the greenery healthy and the system in balance.” Hoogendoorn is installing the entire pipe network, the ‘Rain Manager system’ and various pump installations.
Prefabrication wherever possible
At Hoogendoorn’s workshop in Woerden, work is already well under way. Complete sections of the drainage system are prefabricated here using the Geberit PE system. “We weld them together completely in our workshop, so they can be installed on site in one go,” Karels explains. “We build the water pipes on site instead, to prevent damage during transport. That way, we combine speed with reliability.”
Involved from the foundations
Hoogendoorn has been a visible presence on site since September 2024. During the structural phase, pipes were already cast into the basement floors and foundations. Most of the first-fix pipework for water and drainage has also been installed on the upper floors. The focus is now on fitting out the toilet facilities, a phase in which all the planning comes together.
Building reliability together
Linden shows how smart installations, prefabrication and sustainable water use can reinforce one another. For Hoogendoorn, it is above all a project built on collaboration, planning and craftsmanship. Not by making a big thing of it, but simply by doing the job well. And that is precisely what will make this ING headquarters ready for the future.
Question about this story? Ask your question
Who worked on ING Hoofdkantoor
- façade contractorRollecateMentioned in ING Headquarters, Amsterdam | High standards for safety and sustainability
- aluminium canopiesSorbaMentioned in ING Headquarters, Amsterdam | High standards for safety and sustainability
- building services consultantDeernsMentioned in ING headquarters, Amsterdam | Integrated design down to the level of building use
- sanitary installationsSanitair-Installatie Hoogendoorn B.V.In this story
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectING Hoofdkantoor
- SubjectModular construction
- CompanySanitair-Installatie Hoogendoorn B.V.