UGO Apeldoorn is ready for the future

Text Ramona KezerImage Van Norel Bouwgroep

Waar mogelijk werden materialen hergebruikt.
Waar mogelijk werden materialen hergebruikt.

Renovation and revitalisation of a school building

Van Norel Bouwgroep renovated and revitalised the building of UGO, a lower secondary pre-vocational school in Apeldoorn. The school’s layout was adapted to make it better suited to practical education. The building was also insulated. In addition, Van Dorp Amersfoort carried out numerous electrical and mechanical engineering works as a separate contractor.

The building was also insulated.

Van Norel Bouwgroep project manager Martin Heutink: “The client decided to tender the two parts of the work separately. We took the lead and set the schedule.” UGO uses learning commons, and the layout of the existing building no longer met its needs. “We started in early September 2023, and the school had to be ready before the end of that school year. We managed it, of course, despite having to adjust the schedule several times. In the end, the removal company was ready and waiting the day after handover.” 

Reused materials

As well as adapting the building’s layout, Van Norel provided the necessary facilities for the new building services. The ventilation system was renewed, and large ducts had to be brought into the building to meet current requirements. The contractor therefore made sizeable openings to allow the ducts to be installed. As the ventilation system runs above the ceilings, several thousand m2 of ceiling had to be replaced too. “Throughout the project, we carefully considered what was needed. Where no work was required, we replaced nothing. This was partly due to the budget, but also for sustainability reasons. For example, we temporarily stored ceiling tiles that were still in good condition in the basement, then reused them later. There is some colour variation, but the client was happy with that. We also reused various doors and frames within the building.” The roof was insulated too: Van Norel installed 2,500 m2 of insulation and replaced the roof covering. 

The school is now ready for the future.

‘An old building brings surprises’

Finally, the school was refreshed by painting the walls and renewing the floor finishes. New PVC flooring was installed in several areas. The building dates back to the 1960s, which brought a few surprises. Heutink: “We came across a few things we hadn’t anticipated.

Sometimes the structure had been built differently from what the drawings showed. Requirements, for example for fire safety, have also become much stricter over the years. So we had to carry out quite a bit of additional work to bring the building up to date. The biggest challenge was completing all of this within the time available.” 

Fortunately, Van Norel Bouwgroep can count on reliable partners. “That includes the flooring contractor, the painting company and coordinating with the building services contractor. It was an intensive project that required a great deal of discussion and coordination. This included working with the client, as additional work kept being added, and costs rose accordingly. The school can now look ahead to another 25 years, with lower energy consumption and facilities suited to the future. The school was officially opened by the alderman at the end of September. We were there and treated the teachers and pupils to ice cream. They are delighted with the renovated building.” 

Question about this story? Ask your question

Wie aan UGO werkte

  1. separate contractorVan Dorp AmersfoortIn this story
  2. electrical and mechanical installationsVan Dorp InstallatiesMentioned in Working to a tight deadline

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectUGO
  • SubjectEducation
  • CompanyVan Dorp Amersfoort
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.