Residential and non-residential construction
The finished City Icoon is becoming increasingly visible
Text Lieke van ZuilekomPhotography Catch Your Moment and Heddes Bouw & Ontwikkeling

Finishing work has begun on City Icoon, in a unique location between the IJ and the Tolhuiskanaal, in the Buiksloterham area of Amsterdam-Noord. Commissioned by developer Amvest and designed by Studioninedots, Heddes Bouw & Ontwikkeling is delivering a distinctive new-build development with 122 rental apartments and commercial spaces. Instead of a single massive volume, the architectural practice designed two slender towers, also known as the ‘360 Twins’, which merge at their base with a terraced podium. A basement car park is being built beneath the podium. The new-build development is due for completion in the summer of 2022.
Heddes Bouw & Ontwikkeling focuses on contracts that include engineering and design responsibility. “For the City Icoon project, we used the pre-construction phase to make the work feasible in terms of construction and cost, for example by optimising building systems and materials. We began construction in March last year,” says project manager Piet Wever.

Traditional core, tunnel-formed towers
A sheet-pile wall was already in place along the water, and Heddes Bouw & Ontwikkeling connected the sheet-pile wall for the construction pit to it. “This is one of the areas where a different system was chosen from the one originally designed,” says Wever. “The initial plan was to install a sheet-pile wall with bracing, but a design incorporating relief trenches enabled us to replace it with a freestanding sheet-pile structure. As we encountered some soil contamination, this was remediated first. The new-build was then erected on precast piles measuring 50×50, each 21 metres long, driven in from ground level. Once the building had been excavated, we began cropping the piles and constructing the (crane) pile caps and basement floor.” The basement itself was built with cast in-situ walls, wide-slab floors and shoring towers to accommodate the considerable heights. The first and second floors were also built using traditional methods because of the many differences in floor levels. “After that, we began tunnel form construction.”

150,000 kilos of recycled material
The building comprises two towers, each fourteen storeys high. Between them is a central section with stepped facades. “Because of these setbacks, we built the first five floors at the same time,” says Wever. “The towers were then built separately, so that we could start work on the facade and fit-out as quickly as possible.” The structure is being fitted with subframes and aluminium window frames with pivot windows, which can be cleaned easily from the inside. “The facade-closing elements are finished with brick cladding. One notable feature is that the plinth is being built with WasteBasedBricks®. These bricks are made from 100% recycled waste materials, such as discarded bricks, old tiles and old ceramic window frames. This means that 150,000 kilos of recycled material are used in the plinth.”
All the facades of City Icoon are being laid in standard stretcher bond. Four colours of brick are used, becoming progressively lighter towards the top. “The stepped transitions in the brickwork are also carried through.” The precast balconies are only installed as the facade progresses downwards. “This also helps us maintain the pace of the project. It ensures the facade can be built efficiently and avoids damage to the balconies.”

Restricted construction site
The many transitions make construction of the substructure particularly complex. The tunnel formwork is also challenging, because of the numerous openings required for the lift, spiral staircase and stairwell, among other things. “To manage the structural works effectively, we developed the project in 3D/BIM,” says Wever. “We did this from start to finish, working closely with our in-house BIM modellers, design coordinators and partner companies.” He says a second challenge is the restricted construction site. “To ensure optimum logistics, we were able to take a section of the road in agreement with the municipality. We set up a through-loading and unloading area there, where building materials are delivered according to a tight schedule. To avoid disrupting through traffic on Grasweg, we gave back a section on the opposite side of the road by moving the pavement and temporarily widening the carriageways with concrete slabs.”
100% gas-free
Once completed, the new-build will operate 100% gas-free, thanks to the installation of a thermal energy storage system. Low-temperature underfloor heating has been selected as the heat distribution system, and the air-handling units will also be powered by the thermal energy storage system. Solar panels will be installed on top of the towers.
Project information
Developer
Amvest
Architect
Studioninedots
Construction
Heddes Bouw & Ontwikkeling
Question about this story? Ask your question
Who worked on City Campus
- Area developerBPDMentioned in Sales of luxury ‘rooms with a view’ at City Campus on Oosterdokseiland to start soon
- ArchitectUNStudioMentioned in Sales of luxury ‘rooms with a view’ at City Campus on Oosterdokseiland to start soon
- ContractorZüblin Nederland B.V.Mentioned in Sales of luxury ‘rooms with a view’ at City Campus on Oosterdokseiland to start soon
- developerAmvestIn this story
- architectStudioninedotsIn this story
- constructionHeddes Bouw & OntwikkelingIn this story
- Heat recovery unitsFlaktGroupMentioned in Four ventilation systems provide fresh air to City Icoon: optimal comfort and health
- Heat recovery unitsVascoMentioned in Four ventilation systems provide fresh air to City Icoon: optimal comfort and health
- mechanical ventilation unitsClimaRadMentioned in Four ventilation systems provide fresh air to City Icoon: optimal comfort and health
- car park ventilationHC PSMentioned in Four ventilation systems provide fresh air to City Icoon: optimal comfort and health
- BALQOON® balcony systemsGranito BetonproductenMentioned in Lightweight balconies for City Icoon installed at the very last moment
- construction partnersInstallatie Combinatie ODE (ICO)Mentioned in An innovative, compact building services concept based on the human body
- developerBPD GebiedsontwikkelingMentioned in An innovative, compact building services concept based on the human body
- lead interior architectHofmanDujardinMentioned in An innovative, compact building services concept based on the human body
- Project managementCBRE NederlandMentioned in An innovative, compact building services concept based on the human body
- Installation partner
Van den Pol ElektrotechniekMentioned in A distinctive building services concept for Booking.com City Campus - mechanical installationsKlimaatservice HollandMentioned in A distinctive building services concept for Booking.com City Campus
- DO+ designTechniplanMentioned in A distinctive building services concept for Booking.com City Campus
- Thermal and acoustic insulationIsolatiebedrijf Hanenberg BVMentioned in Minimising energy losses, maximising fire safety
- fire-resistant and acoustic sealsBrandpreventie Hanenberg BVMentioned in Minimising energy losses, maximising fire safety
- climate ceilingsIntecoMentioned in Comfort, functionality and design come together in Booking.com’s climate ceilings
- clientBooking.comMentioned in Comfort, functionality and design come together in Booking.com’s climate ceilings
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCity Campus
- SubjectResidential and non-residential construction
- CompanyAmvest
- CompanyStudioninedots
- CompanyHeddes Bouw & Ontwikkeling


















