Hoog Lindoduin | A future-proof climate solution for Hoog Lindoduin

Itho Daalderop has been involved in improving the sustainability of the Hoog Lindoduin residential building in Scheveningen since February 2018. As an adviser and manufacturer of innovative climate systems, Itho Daalderop has been working with housing association Vestia and contractor BAM Wonen from this early stage to develop a future-proof climate solution.
“Vestia wants to make its housing stock more sustainable and CO2-neutral by 2050,” says Francois Longayroux, project adviser, Project Sales at Itho Daalderop. “We offer a complete solution for that. We go beyond eliminating the gas connection. We offer a complete solution based on thermal energy storage and ventilation with heat recovery.”
Sixty boreholes
For a properly functioning thermal energy storage system, 138 boreholes would normally need to be drilled around Hoog Lindoduin. “There isn’t enough space,” says Longayroux. “That is why deeper boreholes and double ground loops were chosen. There will now be sixty boreholes, each 240 metres deep.” The boreholes will be connected to water-to-water heat pumps, one for each home, which provide both heating and cooling through the underfloor system. Connected to a 150-litre storage cylinder, the heat pumps also supply hot water to the homes.
Heating and cooling
“The fifth generation of Itho Daalderop heat pumps, the WPU 5G, is being installed on this project,” says Longayroux. “This is our latest generation of heat pumps, with the highest efficiency on the market. They are extremely quiet and very compact. A major advantage is that this heat pump can both heat and cool. When the outdoor temperature is high enough, the heat pump switches automatically from heating to cooling.” Cooling is passive. Heat is extracted from the home through the underfloor system and returned to the ground. This regenerates the ground source, recharging it for the next heating season. Longayroux says: “Only the circulation pump operates during cooling, making it very energy efficient.”
Balanced ventilation with heat recovery
“The underfloor heating distributes heat evenly throughout residents’ homes,” Longayroux continues. “It is important to use a good ventilation system that retains as much heat as possible in the home.” For the homes in Hoog Lindoduin, Itho Daalderop recommended the HRU ECO 300 Optima CO2. This balanced ventilation system with heat recovery achieves an efficiency of 97%. It is a demand-controlled ventilation system based on CO2 levels. A humidity sensor is also installed in the bathroom.

(Image: Jan Spunter)
Installation and commissioning
Itho Daalderop and its project partners are still hard at work on the engineering of the systems for Hoog Lindoduin. BAM Energy Systems is responsible for installing the thermal energy storage system, including the heat pumps. Feenstra is undertaking the ventilation installation. “Together with BAM staff, we commission the heat pumps and provide the associated instruction and training,” says Longayroux. “We also inform residents about how to use the system during residents’ meetings organised by Vestia.”
Longayroux is very positive about the collaboration with Vestia: “Vestia has once again chosen to use our proven complete solution. We are proud to be able to contribute to this landmark project in this way.”
Have a business enquiry for Itho Daalderop? Get in touch
Who worked on Hoog Lindoduin
- housing associationVestiaIn this story
- contractorBAM WonenIn this story
- ventilation installationFeenstraIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHoog Lindoduin
- SubjectResidential and non-residential construction
- CompanyItho Daalderop
- CompanyVestia
- CompanyBAM Wonen
- CompanyFeenstra