600 tonnes of steel for high-bay warehouse structure

Text Johan DebaerePhotography Tasche Staalbouw

Tasche Staalbouw was verantwoordelijk voor de engineering, productie, levering en montage van de staalconstructies voor het hoogbouwmagazijn in Almelo.
Tasche Staalbouw was verantwoordelijk voor de engineering, productie, levering en montage van de staalconstructies voor het hoogbouwmagazijn in Almelo.

When a main contractor is happy with its collaboration with subcontractors, it often works with the same partners on similar projects.

That is why main contractors often contact Tasche Staalbouw to build steel structures. The specialist from Albergen was also involved in constructing the automated high-bay warehouse for Eurol in Almelo.

“It’s a relatively simple hall with a floor area of 12,500 m². But it is 19 metres high, which presents its own challenges. As the main contractor contacted us at an early stage, we were able to contribute to the design of the steel structure. We were responsible for the engineering and production of a powder-coated steel structure, using around 600 tonnes of steel in total,” says Coen Wesselink, general manager and project manager at Tasche Staalbouw. “Our own installation teams carried out the work on site. We carefully considered the best way to assemble the structure and decided to build it from the four corners. The components were manufactured in several phases and then delivered to the site just in time. The loads were carefully planned so that the installers received exactly the elements they needed for assembly. Careful preparation and communication were crucial to achieving a perfect result.”

At Tasche, they know exactly how to approach a project like this. The family business has been active in steel construction and livestock housing for 85 years. “Our Steel Construction division specialises in engineering, manufacturing, supplying and installing steel structures for industrial halls, livestock buildings, non-residential buildings and housing,” Wesselink concludes. “Everything is designed and manufactured using 3D modelling, reducing the risk of errors to an absolute minimum.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.