Construction projects

IKC De Trampoline: Sustainable new-build blends seamlessly into its green surroundings

Text Lieke van ZuilekomFotografie Erik Boschman Fotografie

Dankzij de groene kleur gaat het gebouw als vanzelf op in het buitenterrein.
Dankzij de groene kleur gaat het gebouw als vanzelf op in het buitenterrein.

Quality, flexibility and sustainability were key priorities throughout the design and construction of Integraal Kindcentrum (IKC) De Trampoline. A carefully considered choice of materials and colours helps the building blend seamlessly into its green surroundings. The demountable construction method also aligns closely with the client’s sustainability ambitions….

The sports hall.

Commissioned by schools group Lucas onderwijs under a UAV contract, contractor BUKO bouwsystemen of Vuren was responsible for the detailed design, engineering, construction and all building services for IKC De Trampoline. “As an additional commission, we also supplied the fixed furniture and the permanent fixtures in the sports hall,” says project manager Henk Oomen. “Working in a design team with the schools group and its architect, we developed the preliminary design into a final design. We also took care of the Engineer & Build and permitting processes. During the preparatory phase, we had to work with a large number of stakeholders. The project had broad support from both the client and user sides, which created a distinctive dynamic and a great deal of interaction.”

Tiered steps in the main entrance.

Flexible layout

Before construction could begin, a number of trees were felled on behalf of the municipality. Part of the site was also excavated, after which BUKO bouwsystemen installed the pile foundations and concrete foundation with hollow-core slabs. “We built a steel frame on top of the concrete foundation, with timber-frame walls as infill,” says Oomen. “This enabled us to erect the entire building in a very short time. The steel frame and non-load-bearing internal walls also allow the building to be laid out freely.”   

Strong vertical articulation

The external façade is finished with green metal façade panels. A strong vertical articulation was chosen, with a rhythm of approximately 1.15 metres between the lines. Oomen: “The green colour allows the building to blend naturally into the grounds, which were landscaped in a very natural way by landscape gardener Van der Heijden and playground specialist Speelmaatje. Before construction began, we organised an information day for local residents together with Speelmaatje and the client, giving neighbours a clear picture of what was going to be built.”

In consultation with DAT-architecten, feature walls in a specific shade of green were added in selected rooms.

White with green accents

Alongside the education and childcare centre, IKC De Trampoline includes a sports hall and a large central entrance with tiered steps. Most of the rooms have white painted walls, says Oomen. “For protection, the lower 1.5 metres are also finished with a special coating that is both robust and easy to clean. In consultation with DAT-architecten, feature walls in a specific shade of green were added in selected rooms. The same colour appears on a select number of internal doors and on the folding partition wall, which can separate the entrance from the playroom.”

High-performance thermal insulation contributes to Rc values of 4.5 for the walls and 6.0 for the roof, says Oomen. “Solar panels on the roof also provide sustainable energy generation. Combined with low-temperature heating, heat recovery ventilation and LED lighting with motion sensors, the building comfortably meets the BENG and Frisse Scholen requirements.”  

Project information

Focus on quality and sustainability

Immediately after the autumn half-term break in 2020, Basisschool Trampoline and childcare provider Vlietkinderen moved into the new Integraal Kindcentrum (IKC) De Trampoline in Leidschendam. Quality and sustainability were key priorities throughout the design and construction. The mechanical building services and control systems installed by TGO Technische Installaties make a significant contribution.

“Commissioned by contractor BUKO bouwsystemen, we designed, engineered and installed the climate control systems, water pipes, drainage, rainwater downpipes and sanitary facilities, including the associated control systems,” says project manager Sjoerd Jansen. “The entire new building runs entirely on electricity. An air handling unit on the roof supplies and extracts sufficient fresh air, while an air-to-water heat pump provides efficient heating and cooling. Underfloor heating and cooling were chosen as the room-level emitters.”

He says the main challenges on the project were the very limited spaces available for services. “The schedule was also tight. To maintain the pace of the project, for example, the drainage system was prefabricated. We also held regular coordination meetings with the contractor and other building services contractors. Together, we delivered a fantastic project!”

Project information

Tailored shading for IKC De Trampoline

The sun-facing façades of Integraal Kindcentrum (IKC) De Trampoline in Leidschendam are fitted with high-quality, wind-resistant external screen blinds. Commissioned by contractor BUKO bouwsystemen, Van Berchum Zonwering supplied and installed these face-fixed screens. The shading specialist from Werkendam also provided blackout roller blinds for the central space.

“The polyvinyl-coated glass-fibre screen fabrics on the sun-facing façades are finished in flax grey,” says director Dirk van Berchum. “Education and childcare staff can operate the screens easily using electric switches. Vertical guide rails keep the fabric firmly in place in windy conditions. The screens do not flap, helping to ensure a long service life without damage. The guide rails also prevent oblique sunlight from entering, as they cover the entire window surface.”

Van Berchum Zonwering fitted the central space with roller blinds made from blackout fabric. “Here, too, side guide rails have been incorporated into a cassette system. The highest blinds can be operated easily with a remote control, providing optimum ease of use.”

Construction information

Client 
Scholenkoepel Lucas onderwijs

Users 
Basisschool Trampoline and childcare provider Vlietkinderen

Architect 
DAT-architecten

Project management and supervision 
BOAG

Contractor 
BUKO Bouwsystemen

Building services subcontractors
TGO Technische Installaties (mechanical services and controls) and Reith Elektrotechniek (electrical services)

Landscaping 
Van der Heijden and Speelmaatje

Construction period 
October 2019, September 2020

Vraag over dit verhaal? Ask your question

Wie eraan werkte

IKC De Trampoline in Leidschendam-Voorburg

  1. opdrachtgeverScholenkoepel Lucas onderwijs
  2. architectDAT-architecten
  3. directievoering en toezichtBOAG
  4. contractorBUKO Bouwsystemen
  5. onderaannemers installatiesTGO Technische Installaties
  6. onderaannemers installatiesReith Elektrotechniek
  7. buitenterreinVan der Heijden
  8. buitenterreinSpeelmaatje
  9. zonweringsspecialistVan Berchum Zonwering

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectIKC De Trampoline
  • OnderwerpConstruction projects
  • CompanyScholenkoepel Lucas onderwijs
  • CompanyDAT-architecten
  • CompanyBOAG
  • CompanyBUKO Bouwsystemen
  • CompanyTGO Technische Installaties
Deel dit artikel

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.