Construction projects

Integrated Childcare Centre Ter Aar: Four storeys, one below ground level

Text Liliane VerwooldeFotografie De Vries en Verburg Bouw

Het gebouw wordt opgetrokken met een staalconstructie en houtskeletbouwelementen.
Het gebouw wordt opgetrokken met een staalconstructie en houtskeletbouwelementen.

De Vries en Verburg is building the new Integrated Childcare Centre (IKC) with sports hall in Ter Aar. The IKC will serve a broad range of functions for Ter Aar residents. Alongside childcare and education, it will include a sports hall with catering facilities and a library.

The municipality of Nieuwkoop wanted to bring education, childcare and pre-school care together as a coherent whole in the Integrated Childcare Centre (IKC) with sports hall. In 2021, three primary schools, De Vosseschans, De Fontein and Het Kompas, will move in, along with childcare organisations, the Youth and Family Centre (CJG), a sports hall with catering facilities and Rijn en Venen library.

Two metres below the groundwater table

To build a sports hall while staying within the maximum permitted building height, architecture firm De Zwarte Hond designed a basement level. This meant construction for De Vries en Verburg began two metres below the groundwater level. “To build the basement, we first enclosed the plot with sheet piling,” says André de Geus, project manager at De Vries en Verburg. “We then installed drainage and dewatering systems within the sheet-piled area. Thanks to the hot, dry summer, work below ground level went smoothly.”

The external walls will have a brick plinth.

Limited space

With three building sections and little room around the future building, De Vries en Verburg had to make clever use of the available space. “There was no room beyond the facade lines for the mobile cranes we needed to cover the entire construction site,” says De Geus. “So we positioned them in the future heart of the IKC and built the left and right wings first. We then constructed the central section.”

Challenging connections

The building is constructed with a steel frame and timber-frame elements. The external walls will have a brick plinth, topped by vertical aluminium fins, with timber cladding infill. De Geus says: “It sounds simpler than it is. Following the tender, the specification went through several rounds of cost-cutting, resulting in a wide variety of materials being selected. Add the pitched roofs and changes in height, and it is clear that we are dealing with many non-standard details. Making the building watertight is a challenge.”

Those same rounds of cost-cutting have, however, made it possible to finish the building to a high standard. Around mid-2021, Ter Aar residents will have a beautiful, high-quality meeting place.  

Project information

Client Municipality of Nieuwkoop
Structural engineer BREED Integrated Design, The Hague
Detailed structural design JVZ Ingenieurs, Deventer
Architect De Zwarte Hond, Rotterdam
Contractor De Vries en Verburg, Stolwijk
Construction period April 2020-June 2021 

Vraag over dit verhaal? Ask your question

Wie eraan werkte

Integraal Kindcentrum Ter Aar in Nieuwkoop, nieuwbouw

  1. OpdrachtgeverGemeente Nieuwkoop
  2. ConstructeurBREED Integrated Design, Den Haag
  3. Uitwerkend constructeurJVZ Ingenieurs, Deventer
  4. ArchitectDe Zwarte Hond, Rotterdam
  5. ContractorDe Vries en Verburg, Stolwijk

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectIntegraal Kindcentrum Ter Aar
  • OnderwerpConstruction projects
  • CompanyGemeente Nieuwkoop
  • CompanyBREED Integrated Design, Den Haag
  • CompanyJVZ Ingenieurs, Deventer
  • CompanyDe Zwarte Hond, Rotterdam
  • CompanyDe Vries en Verburg, Stolwijk
Deel dit artikel

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.