Construction projects

Seamless floor insulation, installed quickly and smoothly

Text Patricia van der BeekPhotography Pluimers Isolatie

Installing floor insulation beneath the concrete floor.
Installing floor insulation beneath the concrete floor.

Beneath the concrete floor of Christelijk Lyceum Veenendaal is a 9-centimetre-thick layer of rigid polyurethane foam (PUR) insulation.

Pluimers Isolatie installed the floor insulation. Harm Boltjes, Business Market Account Manager at Pluimers Isolatie, looks back on a project that went smoothly.

“The floor insulation covered a total of 800 square metres,” Boltjes begins. “In 2019, we received the enquiry from Burgland Bouw. The insulation had to achieve an Rd value of 3.5. The insulation layer also had to fit seamlessly against the concrete floor. PUR foam was the ideal material for this.”

On-site assessment

He continues: “As with every project, we first visited the site. During this assessment, we take stock of the situation and the client’s requirements. We then use this information to prepare a tailored quotation and installation plan.” Asked about the conditions at Christelijk Lyceum Veenendaal, Boltjes replies: “The floors were level, and the crawl space beneath them was easily accessible. Our team, made up of experienced tradespeople, was able to work efficiently there.”

Impression of Christelijk Lyceum Veenendaal.

High capacity

Alongside its on-site assessments and skilled workforce, Pluimers Isolatie has another advantage: substantial production capacity. “Our lorries travel throughout the Netherlands and beyond every day,” says Boltjes. “For example, if we are asked to supply and install more PUR, we can respond at short notice. That was also the case at Christelijk Lyceum Veenendaal.” Pluimers Isolatie is a major player in the insulation market and an expert in floor insulation (PUR foam and polystyrene beads) and cavity wall insulation. For the commercial market, Pluimers Isolatie offers additional services, including cavity wall anchoring, impregnating external walls and removing cavity wall insulation.

A smooth project

Pluimers Isolatie completed its work at Christelijk Lyceum Veenendaal more than a year ago. “The work went smoothly,” says Boltjes. “Thanks to thorough preparation, our team knew exactly what to do. They were able to get straight to work when they arrived on site. Working closely with the project manager at Burgland Bouw, they quickly and smoothly installed the PUR foam insulation layer beneath the concrete floor.”  

Question about this story? Ask your question

Who worked on Schoolgebouw Christelijk Lyceum Veenendaal

  1. ClientChristelijk Lyceum VeenendaalMentioned in Characterful school building given a new lease of life as a learning environment fit for the future
  2. interior architectEX InteriorsMentioned in Characterful school building given a new lease of life as a learning environment fit for the future
  3. Building contractorBurgland BouwMentioned in Characterful school building given a new lease of life as a learning environment fit for the future
  4. floor insulationPluimers IsolatieIn this story
  5. fire curtainsStöbich Fire Protection BVMentioned in State-of-the-art fire protection that preserves the architectural design
  6. architectNOAHH ArchitectenMentioned in State-of-the-art fire protection that preserves the architectural design

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectChristelijk Lyceum Veenendaal school building
  • SubjectConstruction projects
  • CompanyPluimers Isolatie
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.