Construction projects

Sustainable, CO2-neutral factory for fresh juice and smoothie producer: ‘De Blender’ is almost ready to get started

Text Lieke van ZuilekomPhotography B-Built

De staalconstructie bestaat voor bijna 80% uit duurzame en recyclebare materialen.
De staalconstructie bestaat voor bijna 80% uit duurzame en recyclebare materialen.

Drinks maker innocent drinks aims to be fully CO2-neutral by 2030. To achieve this, the world’s most sustainable healthy drinks factory is being built in Rotterdam. ‘De Blender’ is being constructed using sustainable materials sourced locally.

Many smart measures have also been devised to minimise energy consumption, such as reusing heat. With Rotterdam’s De Europoort industrial and port area as its base, ingredients and products will have to travel much shorter distances, keeping CO2 emissions down. Ingredients that do have to travel further will be transported in the world’s first electric, zero-emission lorries. If all goes to plan, De Blender will reduce innocent’s total carbon footprint by 10 per cent. Plenty of natural light, optimal air quality and carefully controlled temperatures will also make the new building a great place to work for employees, as well as the world’s first WELL-certified factory.

De Blender is set to become a model for sustainable factories and encourage other companies to go the extra mile when building their own factories. The first bottles are due to roll off the production line this autumn. Schipper Vloeren completed the substructure of De Blender, while B-Built is responsible for the entire superstructure. “As co-builder for innocent drinks, we are responsible for the steel structure, intermediate floors, internal walls, windows and doors, roofing and façade finishes, among other things,” says project manager Willie Lievense. “Construction is now 90% complete. We will finish our work this summer.”

The exterior and interior walls of the new building are made of sandwich panels.

A steel structure built in 10 weeks

“Working from the aesthetic designs and in close collaboration with our partner Van den Brink Staalbouw, we contributed to the engineering of the steel structure,” says Lievense. “We were then also awarded the rest of the superstructure work. The steel structure had to be completed in a record time of 10 weeks. That was a major challenge for a distribution centre of almost 20,000 m², but one we met with great success. A truss structure with long spans provides large, freely configurable spaces. We also ensured that the roof and façade cladding fit together seamlessly.”

Saving on labour, materials and CO2

The entire roof of De Blender is being fitted with steel roof sheets, insulation and roofing. The exterior and interior walls of the new building are made of sandwich panels. This was a deliberate choice, says Lievense, as it makes it possible to create a well-insulated façade quickly, without the risk of thermal bridges. “Some of the sandwich panels are fire-resistant and have a rock wool insulation core,” he says. “Horizontal Kingspan sandwich panels have been installed on the external façades. They are fixed invisibly and filled with polyisocyanurate (PIR) rigid foam. This is a perfect fit with innocent drinks’ ambition to be CO2-neutral.    

Choosing sandwich panels also means considerable savings on materials and labour, and therefore on CO2.” The choice of a steel structure supports this aim too. “Almost 80% of the structure consists of sustainable and recyclable materials. For all construction materials, we record exactly what we use, where, how and why.”

High-quality new build with high insulation values

When the production building and its warehouse are completed this summer, innocent drinks will have a high-quality new build with high insulation values. This will help keep energy consumption down, Lievense says. “The remaining energy demand will be met using sustainable energy sources, such as on-site solar panels and off-site wind turbines. These installations will be added at a later stage.” With completion just weeks away, he looks back on a project that went smoothly but was also highly challenging, in part because of the short lead times. “Thanks to good collaboration and coordination with Van den Brink Staalbouw, Mucon and all the other construction partners, we have once again made this project a success, with a very satisfied client as a result.” 

Project information

More than 60 tonnes of stainless steel pipe bridges

De Blender, innocent drinks’ new smoothie factory in Rotterdam, will produce around 400 million bottles of chilled juice a year. Smart, efficient and sustainable, with minimal CO2 emissions.

An extensive network of pipes is being installed to transport all the liquids around the factory. The pipes are supported by stainless steel pipe racks. Commissioned by co-builder B-Built, GP Stainless Group designed, manufactured and installed the bespoke pipe bridges. “B-Built was looking for a skilled, flexible partner with direct lines of communication and short lead times. They also needed a company with the capacity to deliver projects of this scale within a short timeframe,” says Peter Keizer, co-owner of GP Stainless Group. “Using the building drawings and layout sketches, we produced the design and production drawings for all the pipe bridges. Given the stringent quality and food safety requirements, stainless steel was chosen over steel. We processed more than 60 tonnes of stainless steel in just 12 weeks. The first line was delivered and suspended from the roof structure only 5 weeks after the project was awarded.”

Project information

A telling calling card

De Blender by innocent drinks will be one of the world’s first CO2-neutral food factories. “To make this possible, the complex is fully electric, with boilers and heat pumps,” says Robbert Janzen, project manager for Van den Pol Elektrotechniek. “This requires a substantial energy installation. All the energy needed will be generated from renewable sources, including a solar farm on site and off-site wind turbines. We will ensure that both elements, energy consumption and generation, are optimally aligned.”

Trust in our expertise 

As well as the complete low-voltage installation and lighting, Van den Pol is also installing all the power supplies for the machinery. “Our specialism in industrial automation means we are familiar with the specific requirements for food production. That is essential on a project like this. The client has great confidence in our expertise, which makes for a good working relationship.”

The most sustainable in the Netherlands

With its energy-neutral smoothie factory on the Maasvlakte, innocent drinks is underscoring its sustainability ambitions, raising the three Ps (People, Planet and Profit) to the highest level. “It is also a telling calling card for Van den Pol,” says Janzen. “It fits our profile as the most sustainable installer in the Netherlands. We have been installing zero-energy homes for a long time. But just a few years ago, building a CO2-neutral factory would have been unthinkable. It shows how the transition to sustainability is accelerating.”

Project team

Construction management Integrated Food Projects (GB)
Architect Van Aken Architecten
Lead structural engineer Aronsohn
Co-builder, substructure Schipper Vloeren
Co-builder, superstructure B-Built
Steel structure Van den Brink Staalbouw, Barneveld
Walls Mucon Benelux, Etten-Leur
Floor systems Ruys Vloeren

Have a business enquiry for Kingspan Light + Air? Get in touch

Who worked on Blender

  1. structural concrete floorsSchipper VloerenMentioned in Bespoke industrial flooring for ‘the Blender’
  2. superstructure construction partnerB-BuiltIn this story
  3. Sandwich panelsKingspanIn this story
  4. low-voltage installation and lightingVan den Pol ElektrotechniekIn this story
  5. clientinnocent drinksIn this story
  6. Construction managementConstruction management Integrated Food Projects (UK)In this story
  7. ArchitectVan Aken ArchitectenIn this story
  8. Lead structural engineerAronsohnIn this story
  9. Steel structureVan den Brink StaalbouwIn this story
  10. WallsMucon BeneluxIn this story
  11. Flooring systemsRuys VloerenIn this story
  12. pipe bridgesGP Stainless GroupIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlender
  • SubjectConstruction projects
  • CompanyB-Built BV
  • CompanyKingspan Light + Air
  • CompanyVan den Pol Elektrotechniek
  • Companyinnocent drinks
  • CompanyConstruction management Integrated Food Projects (UK)