Construction projects

Sustainable, flexible and smart lighting plan for Jumbo distribution centre

Text Lieke van ZuilekomImage TRILUX Benelux

Toepassing van TRILUX LED-lichtlijnen in de logistiek.
Toepassing van TRILUX LED-lichtlijnen in de logistiek.

Supermarket chain Jumbo will supply around 100 stores from a new national distribution centre (NDC) for products with a longer shelf life. By the end of 2020, all stores in Belgium and the Netherlands are to be supplied from this automated distribution centre. The centre recently received the highest possible BREEAM-NL certification. To achieve this certification, sustainable and energy-saving building materials were used wherever possible. The new build, covering more than 45,000 square metres, features solar panels and an installation that provides so much heat that conventional heating is not needed. LED lighting has also been installed throughout, as part of a modern, balanced lighting plan that intelligently integrates optimal flexibility, dimming, daylight-dependent controls and presence detection.

Commissioned by Kromwijk Elektro, TRILUX Benelux was responsible for the design, production, supply and installation of the LED lighting solutions. “Using the basic plan drawn up by BREEAM experts W4Y and Da Vinci vastgoed BV as our starting point, we developed a tailored lighting plan with recessed LED luminaires for the offices, LED downlights for the corridors, LED trunking systems for the warehouse areas, and suitable LED luminaires for the entrance and restaurant,” says Raymond van Dijken, Sales Manager at TRILUX Benelux. “We took particular account of BREEAM-NL and NEN requirements, including those for colour rendering (CRI), lumen-to-watt ratio, uniformity, lux levels and Unified Glare Rating (UGR). Special optics prevent glare. All the luminaires are controlled by our LiveLink Premium lighting management system, which uses automatic controls to deliver optimum lighting quality and energy efficiency.”

All lighting fixtures were installed as part of a coordinated construction sequence with Bouwbedrijf van de Ven and system integrator Witron.

Smart sensors

“Jumbo wanted the latest lighting management technology, offering maximum flexibility, sustainability and very high energy efficiency,” says Van Dijken. “Our LED luminaires and LED trunking systems are ideally suited to this. Luminaires can easily be added or removed in future as the needs of the spaces change. Light output, dimming levels and operating hours can also be adjusted flexibly. Thanks to smart sensors, the LED luminaires in the offices automatically adjust their light output to the available daylight. Combined with motion sensors, this results in significant energy savings. As soon as the sensors detect movement in a space, the luminaires switch on automatically and immediately to a preset light level, taking the daylight level in the space into account. When staff leave, the luminaires stay on for a few minutes before automatically dimming to the desired background level or switching off.” 

Following the example of the office lighting, a small number of the LED trunking systems in the warehouse have also been fitted with sensors. “In addition, central emergency lighting from Inotec has been integrated into some of our luminaires. In the event of an emergency anywhere in the distribution centre, these luminaires automatically switch to emergency lighting mode. This ensures staff and visitors can always find their way outside safely and quickly.”

All the luminaires are controlled by the LiveLink Premium lighting management system, which uses automatic controls to deliver optimum lighting quality and energy efficiency.

100% predictable maintenance

Specific intelligence is built into all the luminaires, allowing Jumbo to control and read data from all the lighting easily via DALI, Van Dijken explains. “Luminaire data is stored. Cloud connectivity enables remote monitoring, while data can also be easily exchanged with the building management system and third-party platforms. Alongside temperatures, operating status, including on/off, and dimming levels, the system records operating hours. This information allows us to further optimise the lighting plan, determine the expected service life of the luminaires and move towards 100% predictable maintenance.”

All lighting fixtures were installed as part of a coordinated construction sequence with Bouwbedrijf van de Ven and system integrator Witron, the supplier of the storage and order-picking system. “Our project manager, John van Gestel, met weekly with our project partners to discuss progress and coordinate deliveries and work, resulting in a smooth delivery.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.