The supporting force beneath the infrastructure of the A16 Rotterdam project
Text and images Funderingscombinatie Voorbij-Franki

FOUNDATION PARTNERSHIP IS DE GROENE BOOG’S ‘INVISIBLE FRIEND’
“Nothing happens without a foundation.” So says Jan Leen van der Vlies, project director at Franki Grondtechnieken. Together with Voorbij Funderingstechniek, Franki Grondtechnieken forms the foundation partnership contracted by the De Groene Boog construction consortium to carry out the foundation work for the A16 Rotterdam project. Jan Leen van der Vlies, Bart de Lange (project manager for the Voorbij-Franki foundation partnership at De Groene Boog) and Erik Sandifort (project manager at Voorbij Funderingstechniek) talk about a project of phenomenal scale.
Involved from an early stage
“We were involved from the tender stage,” says Van der Vlies.
“For example, we had an engineer calculate predictions for pile driving, vibration and pressing, investigated whether the site could be accessed by the heavy foundation machinery, and contributed to discussions on the final design (DO). We also provided engineering capacity for De Groene Boog to produce the construction design (UO) for 34 cofferdams, namely the north and south approaches and the enclosed section. Together with engineering firm M.U.C. and Hektec, we prepared the UO calculations for the sheet piles, strut frames and anchors.”
A range of activities
The foundation partnership could, figuratively speaking, be seen as De Groene Boog’s ‘invisible friend’. The two companies are highly visible while carrying out the work, but once the project is complete, their work is out of sight. De Lange notes: “At peak times, as many as 33 foundation machines were working at the tunnel at the same time.” The A16 Rotterdam project was divided into three sections. Section 1 was near the airport and included, among other things, the A13 slip roads; section 2 covered construction of the tunnel; and section 3 involved building the flyover over the A20/Terbregseplein. “The project involved a mix of structures, both temporary and permanent,” explains Sandifort. “Our work was therefore very varied: building retaining structures, pressing in sheet piles, installing anchors, using precast piles for foundations (VSP), constructing pile mattresses and building combi-walls. We covered every discipline in our field.”
Rottemeren Tunnel: piles installed with watchmaker’s precision
“To construct the tunnel, we built a sheet-pile cofferdam using sheet piles with a total length of around 7 km. We then installed around 9,000 VSP combination piles along the 2.2 km tunnel route,” De Lange explains. “As for the tunnel, we started with the culvert beneath Bergweg, where the first sheet piles were pressed and vibrated into place in April 2020. Around 7 km of sheet piling, with two longitudinal walls and compartment walls in between. Four types of VSP combination pile were used in the tunnel cofferdam: Octicon 480 core/610 tube, Octicon 430 core/560 tube, #350 core/560 tube, and a type with a 320-square precast core in a 508 tube. The Octicon 480/610 tube is new, and we made special moulds for the cores and drill bit.” Van der Vlies concludes: “The piles in the tunnel cofferdam were installed with genuine watchmaker’s precision.” This exceptionally high level of dimensional accuracy was required because, unlike in traditional construction methods, the underwater concrete floor was built directly as a structural floor on this project. The piles therefore had to be positioned within tight tolerances in every direction, so that the diving teams could install the reinforcement cages underwater over the pile heads, which contained heavy GEWI bars.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction projects


















