Karwei Apeldoorn back in business after lightning-fast rebuild

Eleven months after a devastating fire, a new Karwei has opened in the Zuidbroek district of Apeldoorn. Despite the bad weather, the builders completed a new hall in twelve weeks, on the foundations of the old DIY store. The Karwei branch is slightly smaller.
On 27 November 2018, the 7,000 m² DIY store on Laan van de Dierenriem was completely destroyed by fire. A construction team led by SQ Bouw erected a brand-new building on the existing foundations in record time. It is exactly the same size as the old Karwei, a requirement set by the insurer. However, as Karwei owner Bricorama wanted a slightly smaller store, only 5,200 m² is occupied by Karwei itself, with the rest being let to third parties.
Same foundations
Sander van de Blankevoort, owner of SQ Bouw and project manager for the new build, says the site lay derelict for a long time after the remains of the old building were cleared. “We were commissioned on 7 October to build a new premises, and told that the official opening was scheduled for 18 February. Bear in mind that Karwei itself needs eight weeks to fit out the store, and you realise this was an exceptionally short construction period,” he says. “The only advantage was that most of the foundations were already in place. We had to repair some minor fire damage and lay new foundations for the store entrance, which has been extended outwards. New foundations were also laid for the fire wall.”

The new build was completed in an exceptionally short time.
Three fire compartments
The building itself has a steel frame, with sandwich panels and corrugated steel profiles for the façades, and insulated steel sheets for the roof. The Karwei entrance is a projecting steel structure with curtain walling. One difference from the old building is that it now has three fire compartments. Van de Blankevoort explains: “The Karwei store and the lettable area are separate steel structures, divided by a 120-minute fire-resistant partition wall made of cellular concrete. A further compartment, made of cellular concrete, surrounds Karwei’s staff areas and is fire-resistant for 60 minutes. It contains the changing rooms and toilets on the ground floor, as well as offices and a canteen on the first floor.”
A matter of trust
The exceptionally short construction period is a remarkable achievement. Van de Blankevoort says: “We pulled out all the stops to meet the deadline, and we did it. We started building on 7 October, and despite the appalling weather in November and December, the hall was handed over before Christmas. Some projects require you to get started on trust and take risks. We had that trust with all the parties involved. It also takes a great deal of discussion, fine-tuning the schedule every week and maintaining very close contact with the client, architect, consultants, subcontractors and other contractors.”
Floor poured in stages
Discussions revealed that pouring the floors in three stages would save time. “With two-thirds of the roof still not watertight, we went ahead and poured the first section of floor. It was therefore ready sooner, so the building services contractor could get in earlier with a mobile elevating work platform. We found other ways to dovetail tasks as well. Everyone had a positive, practical attitude, and the atmosphere was very good throughout the build. Otherwise, we wouldn’t have made it.”