Modern building services for the historic ARTIS-Aquarium
Text Lieke BousemaImage Breman Utiliteit Zwolle

The restoration and sustainability upgrade of the ARTIS-Aquarium is a remarkable achievement. The same goes for Breman Utiliteit Zwolle, which installed all the mechanical services on behalf of Salverda Bouw. These range from heating, cooling and ventilation to water supply, drainage, sanitary facilities and building controls, all delivered with respect for the building’s historic character.
“We were involved as early as the tender phase, working with the contractor and electrical services installer to draw up a plan for the restoration and sustainability upgrade,” says Jurjan Veenstra, Project Manager at Breman Utiliteit Zwolle. “Because much of the building had been affected by rising damp and salt crystallisation, it was stripped back to its structure and all its building services. We then rebuilt the aquarium building’s services from scratch.”
A remarkable feat
“We adapted the consultant Halmos’s outline design to fit the historic character of the ARTIS-Aquarium,” says Veenstra. “For example, we routed the air ducts across the historic attic without damaging the vaults. We also had to devise a specific route for the heating pipes and other main distribution pipes, so that we would not have to run them through the historic walls and columns. The most remarkable feat, however, was installing the main heating and cooling distribution unit, which was threaded down from the ridge between the historic roof trusses.”
3D/Revit
“To ensure all the processes ran smoothly, we detailed the mechanical services in 3D/Revit and coordinated them with Salverda Bouw, SDR Elektrotechniek (electrical services) and Hellebrekers (aquarium water treatment),” says Veenstra. “The filter room was a particular challenge, as we had to fit in both Hellebrekers’ pipework, filters and pumps and our main distribution network. In addition, the building controls installed by Breman and Hellebrekers meet here, for example to regulate heating and cooling in the aquariums.”
Alternative materials
Given the salty indoor environment, COOL-FIT energy pipes with a protective PE outer layer were used in the filter room, Veenstra concludes. “The water pipes are made from Comap MultiSkin, and for climate control in the filter room we selected a Rosenberg air handling unit made from composite materials. Colasit plastic air ducts were also used here, preventing salt damage and corrosion and ensuring the installations operate safely and have a long service life. To meet the sustainability target, we opted for a heat pump that can supply hot and chilled water simultaneously. After all, the aquariums contain both fresh and salt water, with different temperature ranges.”
Have a business enquiry for Breman Installatiegroep? Get in touch
Who worked on the ARTIS-Aquarium
- mechanical engineering consultantHalmosMentioned in Smart building services for the historic ARTIS Aquarium
- new water treatment plant
Hellebrekers Water & LeisuretechniekMentioned in A milestone reached: ARTIS-Aquarium is almost ready - complete electrical installationSDR ElektrotechniekMentioned in Bespoke electrical engineering for a unique underwater world
- steel windows and doorsJonkers Stalen KozijnenMentioned in Restoration of ARTIS Aquarium combines historic preservation with modern technology
- over 2,000 square metres of terrazzo flooring
Eterno Minerals of the WorldMentioned in New terrazzo floor for ARTIS-Aquarium - architectOTH ArchitectenMentioned in ARTIS-Aquarium: restoration and sustainability upgrade of a wonder of the world
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectARTIS-Aquarium
- SubjectHVAC
- CompanyBreman Installatiegroep
- CompanyHellebrekers
- CompanySDR Elektrotechniek B.V.