Construction projects

Building on a fruitful partnership

Text Patricia van der BeekPhotography De Vries en Verburg

Building on a fruitful partnership

Nature’s Pride, one of Europe’s largest fruit and vegetable importers, is expanding. A further 21,000 square metres is being added to its existing premises in Maasdijk, which cover around 37,000 square metres. The construction of this new section is reaping the benefits of a sustainable partnership that began to take root in 2013.

The expansion will give Nature’s Pride more space for storing, ripening and packing fresh produce. The new section will house several ripening rooms, a fully automated warehouse and sorting lines with packaging robots. The new build also includes several offices, toilet facilities and twelve loading bays. As in the existing section, sustainability, efficiency and ease of use are central to the design.

Working as a construction team

For the expansion, Nature’s Pride chose the companies that built the existing premises eight years ago: De Vries en Verburg as the main contractor, Klimaatservice Holland for the mechanical services, Mansveld Elektrotechniek for the electrical services and Van Kempen Koudetechniek for the refrigeration systems. Gerben van der Glas is project manager for De Vries en Verburg. He explains: “We are carrying out this work as a construction team. At an early stage, we aligned our work and schedules as much as possible. We are also working closely with ABB, which is responsible for the process installations.”

Familiar with each other and the building

The fact that all the construction team members built Nature’s Pride’s existing premises brings several advantages. “We have an established working relationship,” says Van der Glas. “We work as one team. We know each other and know what to expect from one another. We are also familiar with the building. That is useful, as we are building the new section alongside it. We are connecting to the access ramp. In the new layout, the ramp will also provide access to the extension’s rooftop car park. We had to make some changes to the services beneath the ramp to accommodate the expansion. This was quite a challenge, as operations in the existing building had to continue uninterrupted.”

Concrete and steel

Work on the extension began in September 2020. Van der Glas outlines the work: “The new section is being built on driven piles and a concrete foundation. The ground-floor concrete slab was cast in situ. We built the sprinkler tank and the section alongside the access ramp, where the services are now located, using precast hollow-core slabs. The prefabricated superstructure combines concrete and steel. The intermediate and roof floors were made with hollow-core slabs. The façades are clad in insulated sandwich panels and black corrugated sheeting. The roof accommodates the car park, various building services, a green roof and solar panels.”

BREEAM-NL ‘Excellent’

The green roof converts CO2 into oxygen and removes fine particulates from the air. The solar panels meet a large proportion of the new building’s energy needs. Both features contribute to achieving BREEAM-NL ‘Excellent’ certification. Rainwater reuse is another way of supporting the project’s sustainability ambitions. The new building is also heated and cooled sustainably, using waste heat from the refrigeration systems to heat the ripening rooms and offices. “The building services work is in full swing,” says Van der Glas. “The finishing work is also under way. We expect to hand over the building in the fourth quarter of 2021.”    

Infrastructure works nearing completion

Many of the companies involved in Nature’s Pride’s expansion in Maasdijk also worked on the new build in 2013. Among this established group is JVA Stolwijk, which is carrying out various earthworks, roadworks and drainage works for the new build. 

“We also carried out some work for Nature’s Pride between March and July 2019,” says Erik-Jan van Dam, work planner at JVA Stolwijk. “We installed 20 charging points, 8 waiting bays for lorries and 150 temporary parking spaces for visitors and staff. In March 2020, we began preparations for the new build by diverting the cables and services running alongside the existing building. We prepared the construction site up to the summer of 2020. The site was very wet, almost like a swamp. As the bird-breeding season was about to begin, we had to keep the area ‘bird-free’. We did this with biodegradable tape.” From August 2020, JVA Stolwijk carried out the earthworks for the foundation, followed by installing insulation beneath the in-situ concrete floor and carrying out the earthworks for the internal drainage system. Van Dam adds: “Finally, we installed the drainage and laid the paving around the site. We expect to complete our work after the summer building holiday.”

Sanitary installations almost complete

Dorst Installatietechniek B.V. is responsible for all the plumbing and drainage installations for Nature’s Pride’s expansion in Maasdijk. With the work almost complete, Willem van Rij, director of Dorst Installatietechniek, looks back on a well-run project and a good working relationship.

“We have been involved from the very first section of the foundation,” says Van Rij. “On behalf of our regular partner Klimaatservice Holland, we are installing the rainwater drainage, sewerage, water supply, fire hose reels and dry fire mains. The rainwater drainage is a Pluvia system. In the ripening rooms, drainage is provided by slot drains in the ground-floor slab. These slots collect and drain away the condensation.” With the installations 90 per cent complete, work is progressing to schedule. “As we have come to expect, our collaboration with Klimaatservice Holland is excellent. We also work well with De Vries en Verburg and the other companies. We have already worked with most of them on the new build for Nature’s Pride. Together, we are building successfully on that experience.”

Project details
Client Nature’s Pride, Maasdijk
Architect Architectenbureau Paul de Ruiter, Amsterdam
Main contractor De Vries en Verburg, Stolwijk

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.