Construction projects

Station Ede-Wageningen undergoes a major transformation

Text Annemarie ThönissenImage Van Hattum en Blankevoort BV

Alle kappen liggen op hun plek en de tussenliggende ruimtes worden afgewerkt. (Beeld: Stefan Verkerk)
Alle kappen liggen op hun plek en de tussenliggende ruimtes worden afgewerkt. (Beeld: Stefan Verkerk)

Station Ede-Wageningen is undergoing a transformation. Contractor consortium EdesPoort is building new platforms, tracks, tunnels and viaducts, as well as the new station building and platform canopy. Roy Tijssen, assistant project manager at Van Wijnen, and Mark van der Graaf, project manager for consortium EdesPoort, talk about the project and its challenges.

Overview during TVP week 19-2023. (Image: Mart Stevens Project Fotografie)

Station Ede-Wageningen and its immediate surroundings were due for renewal. Commissioned by ProRail, working with the municipality of Ede and NS, contractor consortium EdesPoort is delivering this challenging area development project. The consortium comprises VolkerWessels Infrastructuur (Van Hattum en Blankevoort and VolkerRail) and Van Wijnen. “There was a lot to do, and all the parties and their specialist knowledge and expertise were needed,” says Tijssen. “Van Wijnen is building the station building, platform canopy and 40-metre-high station tower. VolkerRail is carrying out the trackwork, while Van Hattum & Blankevoort is handling the civil engineering works, including a bridge for pedestrians and cyclists and several underpasses.”

The ‘Obelix’ (a Kirow crane belonging to Volker Rail, unique in the Netherlands) is used to position a track element.

Tunnels, bridges and roads

The project started in April 2021, with work on site beginning in January 2022. “We began by constructing the new passenger tunnel. During a 26-day major possession, we then replaced 3 km of track and track cables. The new 8,000-tonne tunnel was also slid into place during that period. It was moved about 100 metres. We then relaid the tracks so that trains could run again as soon as possible,” says Tijssen. 

In addition to the passenger tunnel, a bridge has been built east of the station, says Van der Graaf. “It is 800 metres east of the station and is for cyclists and pedestrians only. A tunnel connecting to the cycle network is also being built on the west side. It will open during a possession in summer 2024. A great deal has been and is being done in terms of urban design to create an attractive area for cyclists, and this is a fine example.”

The station building and platform canopy

The contractor consortium is now working on the station building and finishing the platform canopy, explains Tijssen: “After the major possession in August 2022, we were able to start building the station. We could also begin assembling the platform canopy at the pre-construction site. The station building has three levels of cycle parking and commercial spaces. It will be completed in November 2023.” 

The station building, platform canopy and station tower are clearly visible here, alongside the two new tunnels (the East and West tunnels) and the existing Alberstunnel.

The platform canopy is distinctive, he says. “It consists of 23 large triangles made from laminated timber beams. Each triangle measures 27 x 27 x 27 metres. We pre-assembled the triangles and installed them above the tracks during two possessions. The canopy continues into the station building and the clock tower next to it.” 

Challenges

The biggest challenges lay in planning and logistics. Van der Graaf explains: “The time frame was quite tight, so we had to think creatively to get everything done within the scheduled periods. Train services have to be suspended completely, and you want to keep these periods to a minimum because of the disruption to passengers.” Tijssen adds: “A lot is fixed in the railway world. Add the technical challenges (load-bearing capacity, spans, existing structures and sliding the tunnel into place) and the time frame, and you have a major challenge.” Van der Graaf says: “Logistically, it was a major operation. In the end, we succeeded by making smart use of the space available. We built the tunnel first on the site of the new station square, then the canopy and finally the square, and that did the trick!”

The ‘switch-over’ will take place next February, says Van der Graaf. “There will be no trains from Tuesday to Friday, as the new station will be brought into operation then.”

Question about this story? Ask your question

Wie aan Treinstation Ede-Wageningen werkte

  1. architectMecanooMentioned in New Ede-Wageningen railway station comes into bloom
  2. architect and structural engineerRoyal HaskoningDHVIn this story
  3. contractorVan Hattum en BlankevoortIn this story
  4. contractorVolkerRailIn this story
  5. contractorVan WijnenIn this story
  6. contractorVolkerWessels InfrastructuurMentioned in Ede-Wageningen station undergoes a complete transformation
  7. steel structuresBuiting StaalbouwMentioned in Six hundred tonnes of steel for Ede-Wageningen Station

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectTreinstation Ede-Wageningen
  • SubjectConstruction projects
  • CompanyRoyal HaskoningDHV
  • CompanyVan Hattum en Blankevoort
  • CompanyVolkerRail
  • CompanyVan Wijnen
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.