Renovation and sustainability upgrades at L-flat require meticulous planning and coordination

Text VlasmanPhotography Vlasman

Renovation and sustainability upgrades at L-flat require meticulous planning and coordination

When L-flat was built in Zeist in 1968, it was unique. With 13 storeys, 728 homes and around 2,000 residents, it could be described as the largest apartment block in Western Europe. Now, more than half a century later, the block is undergoing extensive renovation and sustainability upgrades. Commissioned by main contractor Coen Hagedoorn Bouw, Vlasman is carrying out asbestos removal and stripping out the bathrooms, kitchens and toilets (BKT). This large-scale project will take around two years and requires meticulous planning and coordination, including on the logistics side.

A team of six asbestos-removal specialists from Vlasman is leading the strip-out work. They tackle two homes a day. First, they set up a containment area with a shower unit at the front door. The asbestos-containing materials mainly comprise cord between the heating pipes, the bathroom shaft and the glazing putty around the fanlights. At the same time, an external team is removing asbestos-containing panels from the façade. Once the home has been cleared following a final measurement and visual inspection by the laboratory, the asbestos-removal specialists make way for their colleagues carrying out the strip-out.

The bathrooms, kitchens and toilets are stripped out, including tiles and plasterwork, sanitary fittings and pipework.

The bathrooms, kitchens and toilets are stripped out, including tiles and plasterwork, sanitary fittings and pipework. This is routine work for the Vlasman team, but the distinctive feature of its approach becomes clear above all in the logistics operation. Vlasman uses 660-litre containers to remove waste, which are taken down in the goods lift. Since all the contractors involved use this lift as a route for deliveries and waste removal, meticulous coordination is required. Vlasman has taken this on, along with overall coordination of the separate removal and processing of the various waste streams. 

During the work, some residents are housed elsewhere, while those who remain are provided with a chemical toilet, an emergency kitchen and, if needed, access to a flat with a shower. In this way, one entrance at a time, all the homes in the block are completed, after which the contractor can start rebuilding.  

Project information

Project
Asbestos removal and BKT strip-out at L-flat in Zeist

Client
Coen Hagedoorn Bouw

Duration
February 2021, February 2023

Key features
• 13-storey residential block with 728 homes 
• Asbestos removal and BKT strip-out 
• Waste removal using 660-litre containers 
• Meticulous coordination with contractor(s) and subcontractor(s)
• Overall coordination of the removal of various waste streams
• Work carried out while the building remains occupied

Question about this story? Ask your question

Who worked on L-flat

  1. clientWoongoed ZeistMentioned in ‘A fully renovated home in just 12 days’
  2. building servicesVan der Sluis RenovatieMentioned in ‘A fully renovated home in just 12 days’
  3. contractorCoen Hagedoorn BouwMentioned in Renovation makes iconic L-flat more modern and liveable
  4. asbestos removal and demolitionVlasmanIn this story
  5. paintingVerhoeven VastgoedverbeteraarsMentioned in Maintaining, improving and making more sustainable
  6. vacuum insulated glazingFineoMentioned in Maintaining, improving and making more sustainable

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectL-flat
  • SubjectConstruction projects
  • CompanyVlasman
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.