Construction projects

Complete building services: gas-free and fully in 3D/BIM

De torens voegen een hoogte-accent toe aan de laagbouwwijk Paddepoel.
De torens voegen een hoogte-accent toe aan de laagbouwwijk Paddepoel.

All building services (M&E) at Atlas and House of Groningen are being delivered by Aalbers Installatietechniek of Nieuw-Buinen, including BIM engineering. The construction logistics, using tunnel formwork and building one floor per week, called for a very intensive preparation process, both in design and execution. Project manager Marcel Duimering: “For example, we work with Plegt-Vos using accurate ‘as-built photos’ on site, allowing the 3D design and the result to be compared day by day.”

Text | Jan-Kees Verschuure

Atlas and House of Groningen are heated entirely without gas using the Warmtestad district heating network, with a base hot-water temperature of 70°C. Atlas uses cluster heating and CO2-controlled ventilation with heat recovery; House of Groningen is equipped, among other things, with Climarad ventilation units to ensure an optimal indoor climate.

The biggest challenge was the logistics of tunnel formwork construction, says Duimering. “The schedule was ambitious and had to be adjusted slightly because of coronavirus; we managed the logistics excellently with all the parties involved, despite the unusual circumstances. It is extremely important that the installations are designed entirely in 3D, with construction photos taken every day that can be overlaid on the BIM design. Our site managers checked this every day.”

As many prefabricated installation components as possible were incorporated into the shell construction logistics. “For example, the radiators were taken upstairs in the window reveals before installation. The heating cabinets and plumbing service ducts are supplied prefabricated by the wholesaler. The shell of Atlas is complete, while we still have a few months’ work ahead of us at House of Groningen. Atlas was finished this summer, and House of Groningen will be completed at the end of this year.”

Project information

Integrated approach to finishing work

Commissioned by Plegt-Vos, Heigro is carrying out a substantial part of the finishing work on the Atlas and House of Groningen residential towers. Its own employees and regular subcontractors are supplying and installing partition walls and suspended ceilings and system walls, as well as carrying out plastering and textured coating work.

The two residential towers are being built using tunnel formwork, which requires a tight schedule. Through an integrated approach to activities, Heigro aims to deliver the finishing work sustainably and to a high standard of quality, says Rob Groote. “Our client’s requirements come first. To make the delivery and handling of materials on site as efficient as possible, materials for partition walls and system walls are delivered and installed as a package before the tunnel formwork is placed. This also has significant occupational health and safety benefits, as it avoids unnecessary physical strain; ed. This enables us to ensure that the client’s lean schedule runs smoothly, despite the additional challenge of the building’s height.”

Project information

Fast shell construction based on a complete concept

The entire concrete shell of Atlas and House of Groningen was built using tunnel formwork by Casco Bouw Nederland of Staphorst, including the supply of concrete, reinforcement and formwork. “Working with regular partners who shared our mindset meant we could ensure that everyone worked closely together. The ‘production lines’ also got off to a good start straight away,” says director Jan Hokse.

Casco Bouw Nederland built the floors, including prefabricated cores, shear walls and timber-frame construction, and arranged for finishing materials to be delivered in advance, at a rate of 5 days per floor. The work was carried out in two construction phases. Atlas’s 17 storeys were built from week 40 of 2019 to week 10 of 2020, and House of Groningen’s 23 storeys from week 45 of 2019 to week 28 of 2020. “Tunnel formwork construction is inherently based on lean thinking,” says Hokse. “Getting all the parties involved early in the process leads to a smooth-running construction project, and we achieved that.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.