Thermal treatment process produces clean sand, gravel and filler

A new thermal treatment plant is currently under construction at Vondelingenplaat in the Port of Rotterdam. At this plant, old tar-bearing asphalt, mainly sourced from roads in the Netherlands and neighbouring countries, is fully converted into primary raw materials, electricity and heat. The process is unique in the world.
100% recycling of used tar-bearing asphalt
The turbine building at the thermal treatment plant in Rotterdam consists of two sections: a high-rise section and a low-rise section. The control room will be fitted out in the low-rise section, with computers to control the treatment process and the turbine. This section also houses seven transformers. A steam turbine and a large generator will be installed in the high-rise section.
Thermal treatment
The asphalt is recycled in a rotating rotary kiln at a temperature of around 1,000°C. This high temperature completely burns off all the harmful substances in the asphalt. The thermal treatment process produces clean sand, gravel and filler, ready for reuse. Energy from the hot gases is recovered as steam and converted into electricity by a steam turbine. This innovative approach generates around 210,000 megawatt-hours of electricity per year, enough to supply approximately 50,000 households.

Phase 2 is in full swing.
Collaboration between clients and contractors
Middelwateringbouw is working on both the low-rise and high-rise sections. The low-rise section comprises transformer rooms, a control room and office facilities. The high-rise section comprises the turbine hall. The turbine requires a heavy concrete foundation, built by GMB Haven & Industrie. The building envelope consists of a steel frame clad with sandwich panels and brickwork. “It feels good to take on the construction work as a construction team,” says John van Rees, project manager at Middelwateringbouw. “This is a highly complex project involving the latest technology. For the building work, we are working with our client, GMB Haven & Industrie. What sets this project apart is the way clients and contractors are pooling their expertise to find the best solutions.”
Restricted site
Alongside the innovative challenges, Middelwateringbouw is also dealing with more conventional ones. The turbine building is being constructed on a restricted site, where it is not the only contractor at work. Middelwateringbouw is building one section, while the entire plant comprises several sections being built by different contractors. Cranes, lorries and no fewer than 150 skilled workers move around the site every day to carry out their work. This requires careful logistical planning. “Everything has to be delivered just in time,” says Van Rees. “We are also working in different phases. The final phase of the control room and office facilities is now at the finishing stage.” The client is handling the fit-out of the turbine building itself.
Question about this story? Ask your question
Who worked on Thermische reinigingsinstallatie Rotterdam
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRotterdam thermal treatment plant
- SubjectConstruction projects