Residential and non-residential construction
Fast, efficient construction of internal partitions with gypsum blocks
Text Lieke van ZuilekomPhotography Knauf

Fast, efficient and flexible space planning. And simple logistics and excellent sound insulation, too. It is no coincidence that all non-load-bearing internal partitions in De Zalmhaven I, II and III are built using Knauf gypsum blocks. These include partitions between living rooms and bedrooms, between bedrooms and bathrooms, and walls around service risers. All the gypsum blocks are installed by Eurogips as a subcontractor to BAM Bouw en Techniek, Grote Projecten.
“Using gypsum blocks in high-rise projects is not yet common in the Netherlands,” says Raimond de Vries, product manager at Knauf. “Yet these systems are ideally suited to this type of project. De Zalmhaven demonstrates the many advantages offered by solid, lightweight blocks.” His colleague, technical adviser Patrick Moeken, agrees: “Because our gypsum blocks are installed on the finished floor, design changes can still be made right up to the last minute. Residents can also attach paintings, a television or other loads to the internal partitions without any problems.”

The logistical advantages were a key reason for choosing Knauf gypsum blocks for the De Zalmhaven towers, says De Vries. “Because the fit-out only began after the floor screeds had been laid, all materials had to be transported using the internal lifts. Our gypsum blocks are ideal for this. At an early stage of the project, we sat down with Eurogips and BAM to determine the technical specifications, in accordance with the contract requirements and the Building Decree 2012. This included the minimum sound insulation requirements. Where necessary, we carried out additional tests and prepared reports to substantiate the required sound insulation values.” Frans Quataert, site manager at BAM, found the discussions very positive. “By agreeing the technical and aesthetic details at an early stage, we can avoid unpleasant surprises during construction and afterwards,” he says. “This also ensures optimal comfort for residents.”
Knauf gypsum blocks measuring 7 and 10 cm thick are used in De Zalmhaven, depending on the required sound insulation values, says Quataert. “In some places, double gypsum blocks have been installed, preventing impact sound from travelling through. The gypsum blocks also provide a high level of fire resistance (EI60).” Knauf hydro gypsum blocks are installed in wet areas, where they also provide optimal water resistance. All the gypsum blocks are transported to Rotterdam just in time, says Moeken. “One floor is delivered and completed each week, which requires good service and support. By involving our back-office team closely in the project, we can deliver this.”
De Zalmhaven is due for completion in 2022 and, at over 200 metres, is the tallest residential tower in the Benelux. Its location right next to the Erasmus Bridge makes it a real landmark.
A business enquiry for Knauf? Get in touch
Who worked on Zalmhaven
- architectDam & Partners ArchitectenMentioned in Zalmhaven Rotterdam: Area development at street level
- lifting shedCiviele technieken deBoerMentioned in Zalmhaven, Rotterdam | ‘Uniquely designed lifting shed enhances safety’
- architectVan Dam & PartnersMentioned in Zalmhaven, Rotterdam | World’s tallest residential tower built using prefabricated elements
- structural designBAM Advies & EngineeringMentioned in Zalmhaven, Rotterdam | World’s tallest residential tower built using prefabricated elements
- supplies and installsByldis PrefabMentioned in Zalmhaven, Rotterdam | World’s tallest residential tower built using prefabricated elements
- main contractorBAM Bouw en TechniekMentioned in Zalmhaven, Rotterdam | Controlled construction of one floor per week
- claddingAldowaMentioned in Zalmhaven, Rotterdam | Aluminium cladding adds distinction to the Zalmhaven towers
- development consortiumZalmhaven CV (AM/Amvest)Mentioned in Zalmhaven Rotterdam: A new icon on the horizon
- complete ventilation systems
STEBOMAMentioned in De Zalmhaven, Rotterdam: Ventilation systems help create a comfortable indoor climate - steel door and frame assembliesDalocMentioned in Steel door and frame sets for De Zalmhaven residential towers in Rotterdam
- planning, delivery and installationHSEMentioned in Steel door and frame sets for De Zalmhaven residential towers in Rotterdam
- contractorBAM Bouw en Techniek: Grote ProjectenMentioned in Steel door and frame sets for De Zalmhaven residential towers in Rotterdam
- heat pumpsBAM Energy SystemsMentioned in Innovation across the construction supply chain, setting new standards
- installed byEurogipsIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZalmhaven
- SubjectResidential and non-residential construction
- CompanyKnauf