Where safety, technology and growth ambitions come together…
Text Lieke BousemaImage Kuppens Fotografie

Intracare innovation hub: efficient construction within complex constraints
The new, state-of-the-art innovation hub and production facility for Intracare was completed in May, alongside the A50 in Veghel. The carbon-neutral factory occupies a 15,000 m² site and includes chemical and microbiological laboratories, pharmaceutical GMP+ cleanrooms, an experience centre, production lines, storage areas, R&D facilities and logistical amenities. This expansion means Intracare can once again meet growing demand and secure its capacity for growth in the years ahead.
Bouwbedrijf van de Ven won the project through a tender and was responsible for the entire build, including coordinating the electrical, mechanical and sprinkler systems. Key optimisations were made during the preparation phase, explains project manager Ad van der Linden. For example, the firewater tank was rotated and extra floor channels were added to drain liquids efficiently in the event of an incident. “The liquids are first collected in dedicated anterooms, which are accessible through heavy-duty floor hatches,” he says. “This allows leaks to be dealt with locally and prevents contamination from flowing directly into the main basement. At the same time, the anterooms act as traps, preventing odours and fire from spreading through the channels.”

Seveso establishment
The site in Veghel has been designated a Seveso establishment, meaning that large quantities of hazardous substances are handled there and that strict European safety regulations apply. Oversight therefore rests with the province rather than the municipality. Intracare already had an established relationship with Bouwbedrijf van de Ven, which completed an extension in 2014 and has remained involved since then in smaller projects and alterations.
Designed for growth
The new-build complex alongside the A50 comprises a production hall of approximately 2,866 m², a 779 m² warehouse, a 522 m² PGS-15 storage facility and approximately 2,152 m² of office space across three floors. The office can accommodate around 78 employees in total. The industrial hall includes an open production area with storage facilities and three separate PGS-15 rooms for hazardous substances. The site will have 82 parking spaces, with the option to add 45 more. The production facility has also been designed to accommodate growth wherever possible, says Van der Linden. “This means Intracare can expand by approximately 1,060 m² in the future.”
Floors laid to falls
The new hall has a steel frame, steel roof decking and an insulated concrete plinth topped with sandwich panels, as well as a concrete floor laid to falls. “For the office, we opted for a steel frame with hollow-core slabs for the first and second floors and the roof, as well as an insulated concrete plinth topped with sandwich panels. The PGS rooms, in turn, have 120-minute fire-resistant concrete walls and liquid-retaining doors.” Two of these rooms are equipped with gas extinguishing systems, while one has a sprinkler system. “There is also a separate ATEX room. The production and dispatch floors have been laid to a pronounced fall so that firewater drains directly into the firewater tank.”
A wide range of construction methods and technologies on a small site
One particular challenge was designing the floor channels and their connection to the firewater tank, says Van der Linden. “Because of the liquids used, plastic drains had to be avoided, so concrete solutions were chosen. What makes this new-build project unusual is the number of different construction methods and technologies used in a relatively small area, each with its own requirements, regulations and client preferences.”
Question about this story? Ask your question
Who worked on Innovatiehub Intracare
- complete constructionBouwbedrijf van de VenIn this story
- structural consultantVerhoeven en LeendersMentioned in Structurally connecting, improving and safeguarding
- complete electrical installationTimmers Projecten & ServiceMentioned in Efficient, safe and ready for the future
Keep following this
Get an email when a new story is published. No account needed.
- ProjectInnovatiehub Intracare
- SubjectInnovation & technology
- CompanyBouwbedrijf van de Ven