Sluishuis reaches its full height. Millimetres between theory and practice
Text Tjerk van DuinenPhotography egbertdeboer.com

On Tuesday 28 September, there was something to celebrate on Haringbuisdijk in Amsterdam’s IJburg West. Joined by alderman Marieke van Doorninck (Spatial Development and Sustainability), future residents of Sluishuis and representatives of the construction consortium and developers toasted the building reaching its highest point. To mark the occasion, one of the three tower cranes lowered the traditional topping-out beer. Completion is expected in mid-2022, when residents will be able to move into their 442 apartments.
The distinctive shape of Sluishuis is now clearly visible. A square volume has been built on top of the L-shaped excavation pit, with two wings, the cantilevers, converging at an angle of 40°. The wings meet above the water between the fifth and eighth floors. With this iconic design, the development consortium VORM Ontwikkeling/BESIX RED and designers BIG (Bjarke Ingels Group) and Barcode Architects are responding to demand for a striking gateway to IJburg. The ambitious sustainability requirements have also been more than met: the building is energy-neutral and will be supplied with energy by a thermal energy storage system, a large number of PV panels on the roof and a planned island, with district heating as a back-up.

Structural work and fit-out
Long before the structural frame reached its highest point, the construction consortium VORM Bouw/BESIX Nederland had already begun the fit-out and the installation of the façades using timber frame (HSB) elements. VORM Bouw project manager Anne Ippel says: “The lift core is the highest point. As far as the structural work is concerned, we’re now only working on the walls and floors of the top two residential storeys above the cantilevers. Then the concrete pump can go home. We’ve already completed the installation of the HSB elements on the ninth floor, and the internal fit-out will follow shortly afterwards.”
A new experience
Issue 765 of Stedenbouw took an extensive look at the structural challenges posed by Sluishuis’s enormous cantilever. With most of the structural work now complete, there is an opportunity to look back on a construction process that proved a new experience even for seasoned builders. Ippel says: “You don’t pour a wall at an angle of 40° every day. When pouring the cantilevers, several teams and disciplines are at work, building up the pour in horizontal layers of formwork and concrete. The construction joint has to be kept live and wet, which requires continuous coordination with the concrete batching plant. And it is also a clean finish at the top.”
Cantilevers
For Lieven van Sande, project manager on behalf of BESIX Nederland, Sluishuis has also been an interesting learning project. By way of a reminder, structurally, Sluishuis can be understood as a seesaw. The cantilever rests on enormous compression blocks, which in turn sit on 60-metre-long Tubex piles. As the cantilever’s floors are built (poured) gradually, adding weight to the overhanging section, the building moves towards its equilibrium, with the floors level. Van Sande says: “That is what the theoretical model by the structural engineer Van Rossum tells us. With each new floor, you have to check again whether the model is correct. This is done by monitoring several reference points. Once a floor is complete, the actual settlement is measured before and after the supports are removed, allowing the structure to settle, and compared with the model. So far, settlement has been almost exactly as predicted by the model. Adjustments here and there have been a matter of millimetres.” Ippel says that the composition of the materials also played a part. “For example, you have to take into account that concrete needs different mixes in winter to shorten the turnaround time, achieve the required early strength and prevent cracking. With the cantilevers, it was sometimes a delicate balancing act.”

Timber frame and metal stud
Since weight plays a prominent role in this seesaw-shaped building, lightweight solutions were sought for the fit-out and façades. The only exception was the balcony floors, where this could not be avoided. These are the building’s only prefabricated components (442 in total), each weighing 4 to 6 tonnes, and are attached to the main structure using Isokorf systems. The façades are entirely filled with HSB elements.
Ippel says: “To accommodate settlement during construction, these elements are fixed to the main structure at the bottom with the sill; on the other sides, anchors are tightened to a torque of 6 to 10 kilonewtons, with Teflon plates instead of steel washers, so they can move independently. An expansion detail was also used for the lightweight metal stud walls in the internal finish, to accommodate settlement invisibly. It is very labour-intensive, but works extremely well. The same goes for the façades: achieving accurate dimensions takes a huge number of scans to make everything fit.”
Heat exchangers
Meanwhile, the installers are busy fitting the sustainable building services. In addition to the thermal energy storage system, with district heating as a back-up, all apartments are equipped with their own heat pump for individual control. Heat exchangers in the ventilation ducts and shower drains minimise heat loss, while electricity is supplied by solar panels to be installed across a large part of the roof and on one of the three planned islands.
Both men agree that Sluishuis is a unique project. Van Sande says: “It is a design with many challenges, but so far things have gone well, although you could certainly call it an intensive build.” Ippel attributes this in part to the good teamwork between all the parties involved. “Write this down: you do something like this together, exclamation mark.”
Question about this story? Ask your question
Who worked on Sluishuis
- structural engineerVan Rossum Raadgevende IngenieursMentioned in Sluishuis: Landmark gateway to IJburg
- DevelopmentDevelopment consortium VORM Ontwikkeling/BESIX Real Estate Development (RED)Mentioned in Sluishuis: Landmark gateway to IJburg
- ConstructionVORM Bouw/BESIX Nederland construction consortiumMentioned in Sluishuis: Landmark gateway to IJburg
- Foundations, earthworks and dewateringHeSto v.o.f.Mentioned in Sluishuis: Landmark gateway to IJburg
- Building servicesVan der Sluis Technische BedrijvenMentioned in Sluishuis: Landmark gateway to IJburg
- sheet piling and foundation pilesGebr. van 't Hek B.V.Mentioned in ‘Building on water is a job for specialists’
- groundworks and dewateringRoel van der Stoel B.V.Mentioned in ‘Building on water is a job for specialists’
- engineering consultancyIngenieursbureau HektecMentioned in ‘Building on water is a job for specialists’
- dredgingDe Vries & van de Wiel B.V. (DEME Group)Mentioned in ‘Building on water is a job for specialists’
- tender teamVORM Bouw/BESIXMentioned in Raw aluminium gives Sluishuis a distinctive, natural appearance
- the complete electrical installationElektrotechnisch Bureau (ETB) Cas SombroekMentioned in ‘Integrating electrical services is a major challenge’
- sanitary and ventilation systemsVan der Sluis Woningbouw BVMentioned in Sluishuis: beautiful but challenging
- senior site managerBESIX NederlandMentioned in A comprehensive solution for Sluishuis, a striking landmark
- operating companyNEXT NRGMentioned in ‘Sluishuis gets an energy-efficient and cost-effective climate control concept’
- solar panelsKlimaatgarant SolarMentioned in ‘Sluishuis gets an energy-efficient and cost-effective climate control concept’
- development consortiumVORM OntwikkelingIn this story
- construction consortiumVORM BouwIn this story
- aluminium façade claddingSorbaMentioned in Sluishuis sustainability ambitions extend to its timber façade elements
- timber subframesVan den HondelMentioned in Sluishuis sustainability ambitions extend to its timber façade elements
- facade scaffolding and floor supportsMatemco HulpconstructiesMentioned in 1,100 tonnes of temporary works for Sluishuis Amsterdam
- balcony elements and concrete floorsHCI PrefabMentioned in Cantilevered balconies with thermal breaks
- timber and sheet materialsVan DrimmelenMentioned in ‘Logistics arrangements are key to an efficient construction process’
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSluishuis
- SubjectResidential and non-residential construction
- CompanyVORM Ontwikkeling
- CompanyVORM Bouw