nhow Amsterdam RAI | ‘Fit-out progressed smoothly thanks to tight planning and good collaboration’

nhow Amsterdam RAI | ‘Fit-out progressed smoothly thanks to tight planning and good collaboration’

Metal stud partitions were used primarily to divide up the floors at nhow Amsterdam RAI. All these partitions, around 1,800 square metres per floor, were installed by CBA Tiel B.V.. The fit-out specialist also installed suspended ceilings in the central corridors on every floor.

Pleijsier Bouw approached CBA Tiel during the tender process to work up a price for the fit-out package. Knauf, supplier of innovative fit-out systems and materials and a partner of CBA Tiel, also came on board early. Together, the three companies managed the fit-out from start to finish.

Walls and ceilings

“We installed around 1,800 square metres of various types of metal stud partitions on each floor with hotel rooms,” says René Kiezenberg, estimator and work planner at CBA Tiel. “We also installed just under 400 square metres of metal stud ceilings per floor. The central corridors and lifts have suspended ceilings. There are also several communal floors, such as the ground floor and the 17th and 23rd floors. We installed metal stud partitions and suspended ceilings there too.”

2.5 weeks per floor

CBA Tiel had 2.5 weeks per floor to install all the metal stud partitions and ceilings. During this period, CBA Tiel had to complete the setting-out, install the boards and fit the insulation. Meanwhile, the plumber and electrician had to install their systems. “The schedule was very tight,” says Kiezenberg. “Our work started immediately after the façade units were installed. That was our main challenge. If the façade unit could not be installed, for example because of strong winds, we could not continue either.”

Good progress

CBA Tiel brought the fit-out materials inside via a cantilevered loading platform, through a transport opening in the façade unit. Kiezenberg says: “It was quite a job, especially when you consider that 2.5 lorry loads of plasterboard were delivered every two weeks. And that was in addition to all the associated profiles and insulation material! Even so, progress was good. This was partly thanks to the tight planning and good collaboration with Pleijsier Bouw. That kept things moving and maintained a positive atmosphere. It has turned into a magnificent building. We can all be proud of it.” 

A business enquiry for Knauf? Get in touch

Who worked on RAI Hotel

  1. construction partnerPleijsier BouwMentioned in nhow Amsterdam RAI | ‘Our dream has been realised exactly as we imagined it’
  2. interior finishing specialistCBA Tiel B.V.In this story
  3. design studioINTERIOR-CONSULTMentioned in nhow Amsterdam RAI | Fit-out of Europe’s largest hotel proceeds without a hitch
  4. clientNH HotelsMentioned in nhow Amsterdam RAI | Fit-out of Europe’s largest hotel proceeds without a hitch
  5. interior glassHSM GlasMentioned in nhow Amsterdam RAI | Installing the interior glazing was primarily a logistical challenge

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRAI Hotel
  • SubjectConstruction projects
  • CompanyCBA Tiel B.V.
  • CompanyKnauf
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.